A project leader has realized that two activities in the project cannot be done at the same time because not enough resources are available. Activity 3 is critical and has a duration of 5 days. Activity 4 has 2 days of slack and a duration of 2 days. How will the project leader decide which activity should be scheduled first? a. The activity with the most slack
b. The activity with the least slack
c. The activity with the smallest duration
d. The activity with the lowest identification number
e. The activity with the highest cost

answer
Answers: 3

Other questions on the subject: Business

image
Business, 22.06.2019 01:00, lin550
Throne technical university is looking for three people to work in its plant-biology laboratory. the hiring manager is finding that the most suitable job candidates live in other countries and are not willing to move to the city where the university is located. which situation is the university facing? a. lack of flexible workforce b. surpluses in labor talent c. an appearance of quota systems d. deficits in minimum wage demands
Answers: 1
image
Business, 22.06.2019 23:30, cici170
Miller company’s most recent contribution format income statement is shown below: total per unit sales (20,000 units) $300,000 $15.00 variable expenses 180,000 9.00 contribution margin 120,000 $6.00 fixed expenses 70,000 net operating income $ 50,000 required: prepare a new contribution format income statement under each of the following conditions (consider each case independently): (do not round intermediate calculations. round your "per unit" answers to 2 decimal places.) 1. the number of units sold increases by 15%.
Answers: 1
image
Business, 23.06.2019 04:00, queenkimm26
How do i make quick money as a 13 year. old with no alouence.
Answers: 1
image
Business, 23.06.2019 07:00, Shamplo8817
Select all of the tools you could use to track your expenses. -budget software -spreadsheet -mint© -automatic bill payment -mvelopes®
Answers: 2
Do you know the correct answer?
A project leader has realized that two activities in the project cannot be done at the same time bec...

Questions in other subjects:

Konu
History, 17.07.2019 23:30