A scrum master is responsible for estimating a work package that has a significant amount of uncertainty associated with the time and cost to complete. Due to the uncertainty involved he will be making a low, an average and a high estimate. He is using which estimating approach? A. Apportion method
B. Range estimating
C. Learning curve
D. Parametric procedures applied to specific tasks
E. Template method

answer
Answers: 1

Other questions on the subject: Business

image
Business, 21.06.2019 21:30, elopezhilario6339
He set of companies a product goes through on the way to the consumer is called the a. economic utility b. cottage industry c. market saturation d. distribution chain
Answers: 3
image
Business, 22.06.2019 17:30, monicagalarza
If springfield is operating at full employment who is working a. everyone b. about 96% of the workforce c. the entire work force d. the robots
Answers: 1
image
Business, 22.06.2019 19:30, darkremnant14
Problem page a medical equipment industry manufactures x-ray machines. the unit cost c (the cost in dollars to make each x-ray machine) depends on the number of machines made. if x machines are made, then the unit cost is given by the function =cx+−0.3x2126x31,935 . how many machines must be made to minimize the unit cost?
Answers: 3
image
Business, 22.06.2019 19:40, thomasalmo2014
On april 1, santa fe, inc. paid griffith publishing company $2,448 for 36-month subscriptions to several different magazines. santa fe debited the prepayment to a prepaid subscriptions account, and the subscriptions started immediately. what amount should appear in the prepaid subscription account for santa fe, inc. after adjustments on december 31 of the first year assuming the company is using a calendar-year reporting period and no previous adjustment has been made?
Answers: 1
Do you know the correct answer?
A scrum master is responsible for estimating a work package that has a significant amount of uncerta...

Questions in other subjects: