Project managers typically use , also called analogous estimating or the method when there is a past history of similar projects and rough-cut estimates are needed for strategic purposes two-to-five years out because, as estimating methods go, it is faster and less expensive. Multiple Choice bottom-up, learning curve top-down, range estimating top-down, apportion top-down, phase estimating bottom-up, range estimating

answer
Answers: 1

Other questions on the subject: Business

image
Business, 22.06.2019 16:00, heavenwagner
In microeconomics, the point at which supply and demand meet is called the blank price
Answers: 3
image
Business, 22.06.2019 19:40, ashley4329
Anita has been named ceo of a popular sports apparel company. as ceo, she is tasked with setting the firm's corporate strategy. which of the following decisions is anita most likely to makea) whether to pursue a differentiation or cost leadership strategy b) which customer segments to target c) how to achieve the highest levels of customer satisfaction d) what range of products the firm should offer
Answers: 2
image
Business, 23.06.2019 01:30, Joshuafranklindude
Lee earns $1,482 of interest in 270 days after making a deposit of $15,200. find the interest rate.
Answers: 1
image
Business, 23.06.2019 01:50, angie249
Mart's boutique has sales of $820,000 and costs of $540,000. interest expense is $36,000 and depreciation is $59,000. the tax rate is 21 percent. what is the net income? $146,150 221,200 105,000 139,050
Answers: 3
Do you know the correct answer?
Project managers typically use , also called analogous estimating or the method when there is a pas...

Questions in other subjects: