The actual and budgeted costs for Synergy Inc.'s actual level of activity are as follows: Actual Costs Budgeted Costs
Units produced 1,500 1,500
Direct materials cost $5,630 $5,560
Direct labor cost 1,600 1,540
VOH:
Maintenance 735 640
Power 270 200
FOH:
Grounds keeping 1,450 1,400
Depreciation 500 500
Calculate the flexible budget variance.
a. $295U
b. $70F
c. $50F
d. $345U

answer
Answers: 3

Other questions on the subject: Business

image
Business, 21.06.2019 21:00, nwatase
Resources and capabilities, such as interpersonal relations among managers and a firm's culture, that may be costly to imitate because they are beyond the ability of firms to systematically manage and influence are referred to asanswers: socially complex. causally ambiguous. path dependent. the result of unique historical conditions.
Answers: 3
image
Business, 22.06.2019 14:10, miacervenka
When paul o’neill joined alcoa as ceo, he set a , that there would be zero workplace accidents. a lot of people in the organization thought this was impossible given how dangerous some aluminum-manufacturing jobs are, but alcoa’s safety record improved tremendously. as the board of governors of the american red cross considers planning, one option is to make strategic plans and then direct managers to align tactical and operational plans accordingly. another option is to have planning specialists managers across the organization make their own plans. why might this organization’s executives opt for the latter approach? check all that apply. (a) the environment is a dynamic one, and department and frontline managers can come up with more responsive plans than can central leadership. (b)resources will be better coordinated across the organization in support of the overall strategy.(c) senior leadership will have more control over the organization’s direction. (d)when managers come up with their own plans, they are likely to be more committed to following through on them.
Answers: 2
image
Business, 22.06.2019 21:50, preguntassimples
Assume that (i) setups need to be completed first; (ii) a setup can only start once the batch has arrived at the resource, and (iii) all flow units of a batch need to be processed at a resource before any of the units of the batch can be moved to the next resource. process step 1 molding 2 painting 3 dressing setup time 15 min. 30 min. no setup processing time 0.25 min./unit 0.15 min./unit 0.30 min./unit which batch size would minimize inventory without decreasing the process capacity?
Answers: 1
image
Business, 22.06.2019 23:20, QueenNerdy889
You work as the sales manager for a company that sells office supplies to businesses of all sizes. because the profit margins are razor-thin, you need to ensure that you are getting the very best prices on paper, pencils, pens, post-it notes, and other office supplies from the manufacturers. when reviewing the quarterly profit statement, you realize that your costs are higher than they should be, and you trace the higher costs back to an employee who has been lax about getting competitive bids to ensure the lowest prices. when you conduct your research to determine the reason for the higher costs, and take action to bring those costs back down, in which of the key management processes are you taking part?
Answers: 3
Do you know the correct answer?
The actual and budgeted costs for Synergy Inc.'s actual level of activity are as follows: Actual Co...

Questions in other subjects:

Konu
Computers and Technology, 20.12.2021 09:50
Konu
English, 20.12.2021 09:50