Consider two stations in series. Each is composed of a single machine that requires a rather lengthy setup. Large batches are used to maintain capacity. The result is an effective process time of 1 hour per job and an effective CV of 3 (that is, te 1.0 and cz 9.0). Jobs arrive in a steady stream at a rate of 0.9 job per hour, and they come from all over the plant, so Ca = 1.0 is a reasonable assumption. Now, suppose a flexible machine is available with the same capacity but less effective variability (that is, te = 1.0 and ce^2 = 0.25) and can be used to replace the machine at either station. Requied:
At which station should we replace the existing machine with the new one to get the largest reduction in cycle time?

answer
Answers: 1

Other questions on the subject: Business

image
Business, 22.06.2019 08:30, ansarishaheer2888
Sonic corp. manufactures ski and snowboarding equipment. it has estimated that this year there will be substantial growth in its sales during the winter months. it approaches the bank for credit. what is the purpose of such credit known as? a. expansion b. inventory building c. debt management d. emergency maintenance
Answers: 3
image
Business, 22.06.2019 10:20, itscheesycheedar
The different concepts in the architecture operating model are aligned with how the business chooses to integrate and standardize with an enterprise solution. in the the technology solution shares data across the enterprise.
Answers: 3
image
Business, 22.06.2019 11:10, korban23
Post test question number 9 for entering the job market
Answers: 1
image
Business, 22.06.2019 22:00, lol9691
Gyou are in charge of making the work schedule for the next two weeks. typically this is not a difficult task as you work at a routine 8am – 5pm company. however, over the next two weeks you are required to schedule someone to be in the office each saturday. after contemplating this for a few days you make the schedule and assignments. before posting the schedule for everyone you decide that it is a good idea to meet personally with the two people you have scheduled to work the weekend. what do you say to them? what is your desired outcome?
Answers: 3
Do you know the correct answer?
Consider two stations in series. Each is composed of a single machine that requires a rather lengthy...

Questions in other subjects:

Konu
Mathematics, 23.06.2019 03:50