For an activity in a CPM analysis the Early Start time is 15 and the Late Start time is 20. Which of the following statements is true? a. The duration of this task is zero.
b. The slack for this activity is 20.
c. The activity's late start must happen before its early start.
d. The activity is not on the critical path.
e. The duration of this task is 20.

answer
Answers: 1

Other questions on the subject: Business

image
Business, 21.06.2019 12:30, Queiao4088
When a government sees that local industry is threatened by imports, it can threaten to erect import barriers to stop or reduce these imports. this is an example of a driver of international business activity?
Answers: 3
image
Business, 21.06.2019 20:50, nathand200127
Suppose the price of frozen yogurt, a substitute for ice cream, increases. what happens to equilibrium price and quantity of ice cream? a. the price and quantity of ice cream both increase b. the price and quantity of ice cream both decrease c. the price of ice cream increases and the quantity decreases d. the price of ice cream decreases and the quantity increases
Answers: 3
image
Business, 22.06.2019 04:30, lizdeleon248
Jennifer purchased a house in a brand new development in the outskirts of town. when her house was built, the nearest fire department was nearly 20 miles away. as her neighborhood developed, the density of the community called for a new fire department 1.5 miles away. what effect will the new fire station have on her homeowners insurance premium? a. a new fire department will be more demanding on local taxes. her annual premium will go up. b. the location of a fire department has no bearing on the value of her house. her annual premium will stay the same. c. the new fire department will reduce the risk of financial loss in her home. her annual premium should decrease. d. with a fire department so close (less than 5 miles), financial risk on jennifer’s home practically disappears. she will not need to pay insurance anymore.
Answers: 1
image
Business, 22.06.2019 11:30, kaylabethany
Mai and chuck have been divorced since 2012. they have three boys, ages 6, 8, and 10. all of the boys live with mai and she receives child support from chuck. mai and chuck both work and the boys need child care before and after school. te boys attend the fun house day care center and mai paid them $2,000 and chuck paid them $3,000. mai's agi is $18,000 and chuck's is $29,000. mai will claim two of the boys as dependents. she signed form 8332 which allows chuck to claim one of the boys. who can take the child and dependent care credit?
Answers: 3
Do you know the correct answer?
For an activity in a CPM analysis the Early Start time is 15 and the Late Start time is 20. Which of...

Questions in other subjects:

Konu
Computers and Technology, 23.09.2019 05:30
Konu
World Languages, 23.09.2019 05:30