Project Management Practice ProblemBragg’s Bakery is building a new automated bakery downtown Sandusky. Here are the activities that need to be completed to get the new bakery built and the equipment installed. TIME (WEEK)CRASH TIME (WEEK)EXPEDITING COST/WEEKA-963000BA853500CA15104000 DB, C532000EC1062500FD, E215000
Hint: I have directly provided the crashing cost per unit time.
a. What is the normal project length?
b. What is the critical path in this project?
c. Which activity will you choose to crash first to reduce the duration of the project by one week?
d. What is the project length if all activities are crashed to their minimum?
e. What is the slack for activity D?

answer
Answers: 1

Other questions on the subject: Business

image
Business, 21.06.2019 19:20, williampagan9532
Which of the following statements is true? a. financial investment refers to the creation and expansion of business enterprisesb. economic investment refers to the creation and expansion of business enterprisesc. economic investment refers to the purchase of assets such as stocks, bonds, and real estated. both economic and financial investment refer to the purchase of assets such as stocks, bonds, and real estate
Answers: 2
image
Business, 22.06.2019 03:00, oliviaberta91
What is the relationship between marginal external cost, marginal social cost, and marginal private cost? a. marginal social cost equals marginal private cost plus marginal external cost. b. marginal private cost plus marginal social cost equals marginal external cost. c. marginal social cost plus marginal external cost equals marginal private cost. d. marginal external cost equals marginal private cost minus marginal social cost. marginal external cost a. is expressed in dollars, so it is not an opportunity cost b. is an opportunity cost borne by someone other than the producer c. is equal to two times the marginal private cost d. is a convenient economics concept that is not real
Answers: 3
image
Business, 22.06.2019 10:10, cuthbertson157
conquest, inc. produces a special kind of light-weight, recreational vehicle that has a unique design. it allows the company to follow a cost-plus pricing strategy. it has $9,000,000 of average assets, and the desired profit is a 10% return on assets. assume all products produced are sold. additional data are as follows: sales volume 1000 units per year; variable costs $1000 per unit; fixed costs $4,000,000 per year; using the cost-plus pricing approach, what should be the sales price per unit?
Answers: 2
image
Business, 22.06.2019 12:50, HarleyQuinn117
Performance bicycle company makes steel and titanium handle bars for bicycles. it requires approximately 1 hour of labor to make one handle bar of either type. during the most recent accounting period, barr company made 7,700 steel bars and 2,300 titanium bars. setup costs amounted to $35,000. one batch of each type of bar was run each month. if a single company-wide overhead rate based on direct labor hours is used to allocate overhead costs to the two products, the amount of setup cost assigned to the steel bars will be:
Answers: 2
Do you know the correct answer?
Project Management Practice ProblemBragg’s Bakery is building a new automated bakery downtown Sandus...

Questions in other subjects:

Konu
Mathematics, 22.03.2021 20:00
Konu
English, 22.03.2021 20:00
Konu
Mathematics, 22.03.2021 20:00