The production manager must determine the processing sequence for a total of SEVEN jobs through two machines (M1 and M2) or departments. The same sequence will be allowed in both departments. The manager’s goal is to move the jobs through the two departments as quickly as possible.
(a) Prepare a schedule using SPT for the first department i. e., M1. (1 point)
(b) With the help of a Gantt chart, calculate the total completion time, total idle time and the flowtimes of each job on M1 and M2 using this sequence. (2 points)
(c) Find the optimal sequence using Johnson’s Rule. (1 point)
(d) With the help of a Gantt chart, calculate the total completion time, total idle time and the flowtimes of each job on M1 and M2 using this optimal sequence. (2 points)
Note: You MUST draw a Gantt chart for both sequences in this problem.
Answers: 3
Business, 22.06.2019 15:40, Fire8615
Colter steel has $5,550,000 in assets. temporary current assets $ 3,100,000 permanent current assets 1,605,000 fixed assets 845,000 total assets $ 5,550,000 assume the term structure of interest rates becomes inverted, with short-term rates going to 10 percent and long-term rates 2 percentage points lower than short-term rates. earnings before interest and taxes are $1,170,000. the tax rate is 40 percent earnings after taxes = ?
Answers: 1
Business, 22.06.2019 16:20, milkshakegrande101
There are three factors that can affect the shape of the treasury yield curve (r* t , ip t , and mrp t ) and five factors that can affect the shape of the corporate yield curve (r* t , ip t , mrp t , drp t , and lp t ). the yield curve reflects the aggregation of the impacts from these factors. suppose the real risk-free rate and inflation rate are expected to remain at their current levels throughout the foreseeable future. consider all factors that affect the yield curve. then identify which of the following shapes that the us treasury yield curve can take. check all that apply. a. downward-sloping yield curveb. upward-sloping yield curvec. inverted yield curve
Answers: 1
The production manager must determine the processing sequence for a total of SEVEN jobs through two...
English, 30.05.2021 02:30
Mathematics, 30.05.2021 02:30
Mathematics, 30.05.2021 02:30
Mathematics, 30.05.2021 02:30