The following data is given for the Zoyza Company: Budgeted production (at 100% production capacity) 26,000 units
Actual production 27,500 units
Materials:
Standard price per ounce $6.50
Standard ounces per completed unit 8
Actual ounces purchased and used in production 228,000
Actual price paid for materials $1,504,800
Labor:
Standard hourly labor rate $22 per hour
Standard hours allowed per completed unit 6.6
Actual labor hours worked 183,000
Actual total labor costs $4,020,000
Overhead:
Actual and budgeted fixed overhead $1,029,600
Standard variable overhead rate $24.50 per standard labor hour
Actual variable overhead costs $4,520,000
Overhead is applied on standard labor hours.

The factory overhead volume variance is:
Group of answer choices

$73,250U

$73,250F

$59,400F

$59,400U

answer
Answers: 1

Other questions on the subject: Business

image
Business, 21.06.2019 20:30, ShianHagen5
According to the research in strategic human resources management, answers: firms that are able to use human resource practices to develop socially complex human and organizational resources are able to gain competitive advantage over firms that do not engage in these practices. firms that are able to use human resource practices to develop socially simplistic human and organizational resources are able to gain competitive advantage over firms that do not engage in these practices. firms that are able to use human resource practices to develop socially complex human and organizational resources gain little advantage over firms that do not engage in these practices. firms that are able to use human resource practices to develop socially complex human and organizational resources are at a competitive disadvantage when compared to firms that do not engage in these practices.
Answers: 3
image
Business, 22.06.2019 02:30, milkshakegrande101
The cost of capital: introduction the cost of capital: introduction companies issue bonds, preferred stock, and common equity to aise capital to invest in capital budgeting projects. capital is』necessary factor of production and like any other factor, it has a cost. this cost is equal to the select the applicable security. the rates of return that investors require on bonds, preferred stocks, and common equity represent the costs of those securities to the firm. companies estimate the required returns on their securities, calculate a weighted average of the costs of their different types of capital, and use this average cost for capital budgeting purposes. required return on rate: when calculating om operations when the firm's primary financial objective is to select shareholder value. to do this, companies invest in projects that earnselect their cost of capital. so, the cost of capital is often referred to as the -select -select and accruals, which a se spontaneously we hted average cost of capital wa c our concern is with capital that must be provided by select- 쑤 interest-bearing debt preferred stock and common equity. capital budgeting projects are undertaken, are not included as part of total invested capital because they do not come directly from investors. which of the following would be included in the caculation of total invested capital? choose the response that is most correct a. notes payable b. taxes payable c retained earnings d. responses a and c would be included in the calculation of total invested capital. e. none of the above would be included in the cakulation of total invested capital.
Answers: 2
image
Business, 22.06.2019 15:30, Pooh1189
Uknow what i love about i ask a dumb question it is immediately answered but when i ask a real question it take like an hour to get answered
Answers: 2
image
Business, 22.06.2019 18:30, miller5452
Amanufacturer has paid an engineering firm $200,000 to design a new plant, and it will cost another $2 million to build the plant. in the meantime, however, the manufacturer has learned of a foreign company that offers to build an equivalent plant for $2,100,000. what should the manufacturer do?
Answers: 1
Do you know the correct answer?
The following data is given for the Zoyza Company: Budgeted production (at 100% production capacity...

Questions in other subjects:

Konu
Mathematics, 14.02.2021 14:00
Konu
English, 14.02.2021 14:00