Using a project start time of 0 (or January 1) and a required project com-pletion time of 180 days (or June 30), calculate the ES, EF, LS, and LF times and TS for each activity. If your calculations result in a project schedule with negative TS, revise the project scope, activity estimated durations, and/or sequence or dependent relationships among activities to arrive at an accept-able baseline schedule for completing the project within 180 days (or by June 30). Describe the revisions you made answers powerpoint

answer
Answers: 3

Other questions on the subject: Business

image
Business, 21.06.2019 20:30, saykblahwah309
Long-distance providers are becoming increasingly concerned about certain activities within their industry. various companies come together voluntarily to implement new standards of social responsibility that members must abide by. what seems to be the primary motivation in this case for an increased interest in social responsibility? - because corporations are creations of society, they are responsible for giving back to the communities in which they operate.- these companies have realized it is in their best interest to increase their social responsibility before they are once again subject to stricter regulations.- these companies are using social responsibility as a means to increase their profitability, both short term and long term.- long-distance providers have started taking pride in their industry and its record for social responsibility.- they feel a responsibility to their stockholders, employees, the government, investors, and society as a whole.
Answers: 2
image
Business, 21.06.2019 23:00, naomicervero
Walmart’s scm system walmart is famous for its low prices, and you may have experienced its low prices first-hand. at least, you have probably seen its motto, “always low prices— always.” one of the biggest reasons walmart is able to sell at prices lower than almost everyone else is that it has a superefficient supply chain. its it-enabled supply chain management system is the envy of the industry because it drives excess time and unnecessary costs out of the supply chain. so, because walmart can buy low, it sells low. as a matter of fact, if your company wants to sell items to walmart for it to sell in its stores, you will have to do business with it electronically. if your company can’t do that, walmart won’t buy anything from you. log on to walmart’s web site (), search for supplier information, and find out what walmart’s requirements are for its suppliers to do business with it electronically. prepare a brief summary of its requirements for presentation in clas
Answers: 3
image
Business, 22.06.2019 07:40, kanajahbunn
The cutting department of cassel company has the following production and cost data for july. production costs 1. transferred out 12,300 units. beginning work in process $0 2. started 3,900 units that are 60% materials 62,856 complete as to conversion labor 12,622 costs and 100% complete as manufacturing overhead 23,100 to materials at july 31. materials are entered at the beginning of the process. conversion costs are incurred uniformly during the process. determine the equivalent units of production for (1) materials and (2) conversion costs. materials conversion costs total equivalent units of production link to text link to text compute unit costs. (round unit costs to 2 decimal places, e. g. 2.25.) materials $ conversion costs $ link to text link to text prepare a cost reconciliation schedule. (round unit costs to 2 decimal places, e. g. 2.25 and final answers to 0 decimal places, e. g. 1,225.) cost reconciliation costs accounted for transferred out $ work in process, july 31 materials $ conversion costs total costs $
Answers: 1
image
Business, 22.06.2019 12:50, 20170020
Kyle and alyssa paid $1,000 and $4,000 in qualifying expenses for their two daughters jane and jill, respectively, to attend the university of california. jane is a sophomore and jill is a freshman. kyle and alyssa's agi is $135,000 and they file a joint return. what is their allowable american opportunity tax credit after the credit phase-out based on agi is taken into account?
Answers: 1
Do you know the correct answer?
Using a project start time of 0 (or January 1) and a required project com-pletion time of 180 days (...

Questions in other subjects: