Which one of the following is not correct about job-order costing systems and process costing systems? a. Job order costing systems and process costing systems use similar manufacturing accounts.
b. Job order costing systems and process costing systems have different flow of costs through manufacturing accounts.
C. None of the given answers
d. In process costing systems cost accumulation is done on a department basis.
e. Job order costing systems normally used when there are varieties of products to produced.​

answer
Answers: 1

Other questions on the subject: Business

image
Business, 22.06.2019 12:40, hardwick744
Acompany has $80,000 in outstanding accounts receivable and it uses the allowance method to account for uncollectible accounts. experience suggests that 6% of outstanding receivables are uncollectible. the current credit balance (before adjustments) in the allowance for doubtful accounts is $1,200. the journal entry to record the adjustment to the allowance account includes a debit to bad debts expense for $4,800. true or false
Answers: 3
image
Business, 22.06.2019 21:40, QueenNerdy889
Which of the following comes after a period of recession in the business cycle? a. stagflation b. a drought c. a boom d. recovery
Answers: 1
image
Business, 23.06.2019 02:50, Lacrosse34
Which of the following will be a source of cash flows for a shareholder of a certain stock? i. sale of the shares at a future date ii. the firm in which the shares are held paying out cash to shareholders in the form of dividends iii. the firm in which the shares are held increasing the total number of shares outstanding through a stock split
Answers: 2
image
Business, 23.06.2019 03:20, willia343
You would like to compare your firm's cost structure to that of your competitors. however, your competitors are much larger in size than your firm. which one of these would best enable you to compare costs across your industry? common-size income statement. pro forma balance sheet. statement of cash flows. common-size balance sheet
Answers: 3
Do you know the correct answer?
Which one of the following is not correct about job-order costing systems and process costing system...

Questions in other subjects:

Konu
Mathematics, 10.06.2021 01:50
Konu
Mathematics, 10.06.2021 01:50
Konu
Mathematics, 10.06.2021 01:50
Konu
Social Studies, 10.06.2021 01:50