Business, 22.02.2021 22:50, NeverEndingCycle

Bragg's Bakery is building a new automated bakery in downtown Sandusky. Here are the activities that need to be completed to get the new bakery built and the equipment installed:

ACTIVITY PREDECESSOR NORMAL TIME (WEEKS) CRASH TIME (WEEKS)

A - 6 5

B A 5 3

C A 11 8

D B, C 8 7

E C 3 2

F D, E 5 4

EXPEDITING COST/WEEK

$3,500

3,900

4,200

2,200

2,500

4,800

a) What is the normal project length?

b) What is the project length if all activities are crashed to their minimum?

c) Bragg's losses $3,600 in profit per week for every week the bakery is not completed.

How many weeks will the project take if we are willing to pay crashing cost as long as it is less than $3,600?

answer
Answers: 3

Other questions on the subject: Business

image
Business, 22.06.2019 22:00, hiyagirllyric
Which of the following is the term for something that you can't live without 1. need 2. want 3. good 4. service
Answers: 1
image
Business, 22.06.2019 22:50, esid906
Clooney corp. establishes a petty cash fund for $225 and issues a credit card to its office manager. by the end of the month, employees made one expenditure from the petty cash fund (entertainment, $20) and three expenditures with the credit card (postage, $59; delivery, $84; supplies expense, $49).record all employee expenditures, and record the entry to replenish the petty cash fund. the credit card balance will be paid later. (if no entry is required for a transaction/event, select "no journal entry required" in the first account record expenditures from credit card and the petty cash fund.
Answers: 2
image
Business, 22.06.2019 23:20, QueenNerdy889
You work as the sales manager for a company that sells office supplies to businesses of all sizes. because the profit margins are razor-thin, you need to ensure that you are getting the very best prices on paper, pencils, pens, post-it notes, and other office supplies from the manufacturers. when reviewing the quarterly profit statement, you realize that your costs are higher than they should be, and you trace the higher costs back to an employee who has been lax about getting competitive bids to ensure the lowest prices. when you conduct your research to determine the reason for the higher costs, and take action to bring those costs back down, in which of the key management processes are you taking part?
Answers: 3
image
Business, 23.06.2019 08:30, mez64
In the supply-and-demand schedule shown above, the equilibrium price for cell phones is $25 $100 $200
Answers: 2
Do you know the correct answer?
Bragg's Bakery is building a new automated bakery in downtown Sandusky. Here are the activities tha...

Questions in other subjects:

Konu
Mathematics, 23.10.2020 18:30
Konu
Mathematics, 23.10.2020 18:30