Business, 22.02.2021 19:30, kaylamaisonettt

Letang Industrial Systems Company (LISC) is trying to decide between two different conveyor belt systems. System A costs $265,000, has a four-year life, and requires $73,000 in pretax annual operating costs. System B costs $345,000, has a six-year life, and requires $67,000 in pretax annual operating costs. The company always needs a conveyor belt system; when one wears out, it must be replaced. Assume the tax rate is 21 percent and the discount rate is 8 percent. Required:
Calculate the EAC for both conveyor belt systems.

answer
Answers: 3

Other questions on the subject: Business

image
Business, 21.06.2019 18:20, jrjordans13ox06qs
When someone buys a fourth television for his or her house, what is the result? a. there's a decrease in the marginal utility of the television. b. the increase in demand brings leads to higher prices for televisions. c. the production of televisions becomes more efficient. d. there's a rise in the opportunity cost of buying other goods.
Answers: 2
image
Business, 22.06.2019 00:40, lindseybug
Guardian inc. is trying to develop an asset-financing plan. the firm has $450,000 in temporary current assets and $350,000 in permanent current assets. guardian also has $550,000 in fixed assets. assume a tax rate of 40 percent. a. construct two alternative financing plans for guardian. one of the plans should be conservative, with 70 percent of assets financed by long-term sources, and the other should be aggressive, with only 56.25 percent of assets financed by long-term sources. the current interest rate is 12 percent on long-term funds and 7 percent on short-term financing. compute the annual interest payments under each plan.
Answers: 3
image
Business, 22.06.2019 21:00, nikkiwoodward1ovgszp
Warner inc. sells a high-speed retrieval system for mining information. it provides the following information for the year. budgeted actual overhead cost $965,700 $905,000 machine hours 58,570 49,200 direct labor hours 107,300 104,200 overhead is applied on the basis of direct labor hours. compute the predetermined overhead rate. predetermined overhead rate $ per direct labor hour link to text determine the amount of overhead applied for the year. the amount of overhead applied $
Answers: 1
image
Business, 22.06.2019 22:40, laceysmith2i023
Suppose your firm is considering investing in a project with the cash flows shown as follows, that the required rate of return on projects of this risk class is 10 percent, and that the maximum allowable payback and discounted payback statistics for the project are three and a half and four and a half years, respectively. use the irr decision to evaluate this project; should it be accepted or rejected
Answers: 3
Do you know the correct answer?
Letang Industrial Systems Company (LISC) is trying to decide between two different conveyor belt sys...

Questions in other subjects:

Konu
Mathematics, 22.01.2021 08:40
Konu
Mathematics, 22.01.2021 08:40
Konu
Mathematics, 22.01.2021 08:40
Konu
Mathematics, 22.01.2021 08:40
Konu
Mathematics, 22.01.2021 08:40
Konu
Mathematics, 22.01.2021 08:40