Answers: 2
Business, 23.06.2019 18:30, bunnyqueen124
At december 31, 2018, newman engineering’s liabilities include the following: $29 million of 5% bonds were issued for $29 million on may 31, 1999. the bonds mature on may 31, 2029, but bondholders have the option of calling (demanding payment on) the bonds on may 31, 2019. however, the option to call is not expected to be exercised, given prevailing market conditions. $33 million of 4% notes are due on may 31, 2022. a debt covenant requires newman to maintain current assets at least equal to 194% of its current liabilities. on december 31, 2018, newman is in violation of this covenant. newman obtained a waiver from national city bank until june 2019, having convinced the bank that the company’s normal 2 to 1 ratio of current assets to current liabilities will be reestablished during the first half of 2019. $26 million of 7% bonds were issued for $26 million on august 1, 1989. the bonds mature on july 31, 2019. sufficient cash is expected to be available to retire the bonds at maturity. required: classify the above mentioned debts as current liabilities or noncurrent liabilities. also, provide corresponding value for the same. (enter your answer in millions (i. e., 10,000,000 should be entered as
Answers: 2
Business, 23.06.2019 22:00, Lilyy1k
Just like a lot of other americans, john wayne died of cancer. but is there more to this story? in 1955, wayne was in utah shooting a film. across the state line, in nevada, the united states military was testing atomic bombs. radioactive fallout from those tests drifted across the filming location. a total of 46 of the 220 people working on the film eventually died of cancer. cancer experts estimate that one would expect only about 30 cancer deaths in a group this size. is the death rate among the movie crew unusually high? does this prove that exposure to radiation increases the risk of cancer?
Answers: 1
Business, 24.06.2019 09:20, taloneyes3535
The following is a table of activities associated with a project at rafay ishfaq's software firm in chicago, their durations, what activities each must precede and the crash cost to reduce duration per week: activity duration (weeks) precedes crash cost/week a (start) 22 b, c $ 370$370 b 22 e $ 110$110 c 55 f $ 220$220 e 11 f $ 150$150 f (end) 22 long dash— $ 450$450 suppose that rafay is only given 66 weeks (instead of 99) to complete the project. by how many weeks should each activity be crashed in order to meet the deadline? assume that you can crash an activity down to 0 weeks duration. activity each activity should be reduced by (weeks) a nothing week(s)
Answers: 2
Manufacturing overhead was estimated to be $355,300 for the year along with 20,900 direct labor hour...
Mathematics, 05.01.2021 08:50
Mathematics, 05.01.2021 08:50
Biology, 05.01.2021 08:50
Mathematics, 05.01.2021 08:50
Geography, 05.01.2021 08:50
Mathematics, 05.01.2021 08:50
Advanced Placement (AP), 05.01.2021 08:50