Your boss would like you to estimate the fixed and variable components of a particular cost. Actual data for this cost over four recent periods appear below. Activity Cost
Period 1 32 $388
Period 2 31 $377
Period 3 30 $362
Period 4 35 $406

Using the least-squares regression method, what is the cost formula for this cost?

answer
Answers: 3

Other questions on the subject: Business

image
Business, 21.06.2019 16:50, michellemunoz250
Malcolm has several receipts from recent transactions that he entered in his records. the receipts include an atm receipt for an $80.00 deposit, a grocery store receipt for $25.50, and a paycheck deposit slip for $650.00 when he finishes entering his transactions, malcolm realizes that his balance is incorrect. assuming that malcolm had no beginning balance, what should his correct balance be?
Answers: 1
image
Business, 21.06.2019 18:30, mashejaj
2. high-glow currently produces 1,000 bicycles per month. the following per unit data apply for sales to regular customers: direct materials $50 direct manufacturing labor 5 variable manufacturing overhead 14 fixed manufacturing overhead 10 total manufacturing costs $79 the plant is experiencing demand shortage and is considering reducing production to 800 bicycles. what is the per unit cost of producing 800 bicycles? a) $79 per unit b) $81.50 per unit c) $74 per unit d) $69 per unit
Answers: 2
image
Business, 21.06.2019 18:30, raquelwilliams6912
What’s the best type of healthcare plan
Answers: 1
image
Business, 22.06.2019 07:20, staxeeyy767
Richardson hired j. c. flood company, a plumbing contractor, to correct a stoppage in the sewer line of her house. the plumbing company's 'snake' device, used to clear the line leading to the main sewer, became caught in the underground line. to release it, the company excavated a portion of the sewer line in richardson's backyard. in the process, the company discovered numerous leaks in a rusty, defective water pipe that ran parallel with the sewer line. to meet public regulations, the water pipe, of a type no longer approved for such service, had to be replaced either then or later, when the yard would have to be excavated again. the plumbing company proceeded to repair the water pipe. though richardson inspected the company's work daily and did not express any objection to the extra work involved in replacing the water pipe, she refused to pay any part of the total bill after the company completed the entire operation. j. c. flood company then sued richardson for the costs of labor and material it had furnished. (c) for what, if anything, should richardson be liable? explain."
Answers: 1
Do you know the correct answer?
Your boss would like you to estimate the fixed and variable components of a particular cost. Actual...

Questions in other subjects:

Konu
Mathematics, 25.02.2021 20:00
Konu
Mathematics, 25.02.2021 20:00
Konu
Mathematics, 25.02.2021 20:00