A project has four activities: A, B, C, and D. The budgeted (planned) cost of each activity is $22K, $14K, $12K, and $28K, respectively. The planned percentages complete for the current date are 90%, 80%, 70%, and 20% respectively. The actual percentages complete for the current date are 100%, 90%, 75%, and 10% respectively. The actual cost of the work performed to date is $40K. What is the schedule performance index for the project

answer
Answers: 2

Other questions on the subject: Business

image
Business, 22.06.2019 17:50, nayelieangueira
What additional information about the numbers used to compute this ratio might be useful in you assess liquidity? (select all that apply) (a) the maturity schedule of current liabilities (b) the average stock price for the industry (c) the average current ratio for the industry (d) the amount of current assets that is concentrated in relatively illiquid inventories
Answers: 3
image
Business, 22.06.2019 19:30, mfkinnatz
Dollar shave club is an ecommerce start-up that delivers razors to its subscribers by mail. by doing this, dollar shave club is using a(n) to disrupt an existing market. a. innovation ecosystem b. architectural innovation c. business model innovation d. incremental innovation
Answers: 2
image
Business, 22.06.2019 19:30, sky81428
Which of the following occupations relate to a skill category of words and literacy
Answers: 1
image
Business, 22.06.2019 19:50, wsdafvbhjkl
On july 7, you purchased 500 shares of wagoneer, inc. stock for $21 a share. on august 1, you sold 200 shares of this stock for $28 a share. you sold an additional 100 shares on august 17 at a price of $25 a share. the company declared a $0.95 per share dividend on august 4 to holders of record as of wednesday, august 15. this dividend is payable on september 1. how much dividend income will you receive on september 1 as a result of your ownership of wagoneer stock
Answers: 1
Do you know the correct answer?
A project has four activities: A, B, C, and D. The budgeted (planned) cost of each activity is $22K,...