Cooper Construction Company had a contract starting April 2015, to construct a $18,000,000 building that is expected to be completed in September 2017, at a total estimated cost of $16,500,000. At the end of 2015, the costs to date were $7,590,000 and the estimated total costs to complete had not changed. The progress billings during 2015 were $3,600,000 and the cash collected during 2015 was 2,400,000. For the year ended December 31, 2015, Cooper would recognize gross profit on the building of:

answer
Answers: 1

Other questions on the subject: Business

image
Business, 22.06.2019 12:30, dtrdtrdtrdtrdrt1325
Suppose a holiday inn hotel has annual fixed costs applicable to its rooms of $1.2 million for its 300-room hotel, average daily room rents of $50, and average variable costs of $10 for each room rented. it operates 365 days per year. the amount of operating income on rooms, assuming an occupancy* rate of 80% for the year, that will be generated for the entire year is *occupancy = % of rooms rented
Answers: 1
image
Business, 22.06.2019 15:20, ashleyuchiha123
Gulliver travel agencies thinks interest rates in europe are low. the firm borrows euros at 5 percent for one year. during this time period the dollar falls 11 percent against the euro. what is the effective interest rate on the loan for one year? (consider the 11 percent fall in the value of the dollar as well as the interest payment.)
Answers: 2
image
Business, 22.06.2019 17:00, justyne2004
Afinancing project has an initial cash inflow of $42,000 and cash flows of −$15,600, −$22,200, and −$18,000 for years 1 to 3, respectively. the required rate of return is 13 percent. what is the internal rate of return? should the project be accepted?
Answers: 1
image
Business, 22.06.2019 20:00, 2965276513
Afirm is producing at minimum average total cost with its current plant. draw the firm's long-run average cost curve. label it. draw a point on the lrac curve at which the firm cannot lower its average total cost. draw the firm's short-run average total cost curve that is consistent with the point you have drawn. label it. g
Answers: 2
Do you know the correct answer?
Cooper Construction Company had a contract starting April 2015, to construct a $18,000,000 building...