If the actual labor rate exceeds the standard labor rate and if the actual labor-hours exceed the number of hours allowed, the total labor flexible budget variance will be:. a. Favorable
b. Unfavorable
c. Equal to labor rate variance
d. Unable to be determined

answer
Answers: 2

Other questions on the subject: Business

image
Business, 22.06.2019 07:30, dimondqueen511
Which two of the following are benefits of consumer programs
Answers: 1
image
Business, 22.06.2019 11:10, henryzx900
How much are you willing to pay for a zero that matures in 10 years, has a face value of $1,000 and your required rate of return is 7%? round to the nearest cent. do not include a dollar sign in your answer. (i. e. if your answer is $432.51, then type 432.51 without $ sign)
Answers: 1
image
Business, 22.06.2019 19:40, cieloromero1
Moody corporation uses a job-order costing system with a plantwide predetermined overhead rate based on machine-hours. at the beginning of the year, the company made the following estimates: machine-hours required to support estimated production 100,000 fixed manufacturing overhead cost $ 650,000 variable manufacturing overhead cost per machine-hour $ 3.00 required: 1. compute the plantwide predetermined overhead rate. 2. during the year, job 400 was started and completed. the following information was available with respect to this job: direct materials $ 450 direct labor cost $ 210 machine-hours used 40
Answers: 3
image
Business, 23.06.2019 01:50, maddie7417
You are looking at a one-year loan of $16,500. the interest rate is quoted as 8.7 percent plus two points. a point on a loan is 1 percent (one percentage point) of the loan amount. quotes similar to this one are common with home mortgages. the interest rate quotation in this example requires the borrower to pay two points to the lender up front and repay the loan later with 8.7 percent interest. what rate would you actually be paying here?
Answers: 3
Do you know the correct answer?
If the actual labor rate exceeds the standard labor rate and if the actual labor-hours exceed the nu...

Questions in other subjects:

Konu
Mathematics, 27.05.2021 19:40