What will happen to a project's schedule if there are resource overloads and the critical path is delayed? a. Nothing will happen to the project's schedule if the critical path is delayed.
b. The project's schedule will slip only if the float / slack period for the critical path activities is not enough to resolve the resource overload issue.
c. The project's schedule will slip only if the float/slack period for the noncritical activities is not enough to resolve the resource overload issue.
d. There is never a delay in the critical path, because it is the longest path through the network.

answer
Answers: 1

Other questions on the subject: Business

image
Business, 22.06.2019 10:00, mayamabjishovrvq9
Suppose an economy has only two sectors: goods and services. each year, goods sells 80% of its outputs to services and keeps the rest, while services sells 62% of its output to goods and retains the rest. find equilibrium prices for the annual outputs of the goods and services sectors that make each sector's income match its expenditures.
Answers: 2
image
Business, 22.06.2019 11:00, neash19
Why does an organization prepare a balance sheet? a. to reveal what the organization owns and owes at a point in time b. to reveal how well the company utilizes its cash c. to calculate retained earnings for a given accounting period d. to calculate gross profit for a given accounting period
Answers: 3
image
Business, 22.06.2019 19:50, hallkanay7398
Ichelle is attending college and has a part-time job. once she finishes college, michelle would like to relocate to a metropolitan area. she wants to build her savings so that she will have a "nest egg" to start her off. michelle works out her budget and decides she can afford to set aside $9090 per month for savings. her bank will pay her 4 %4% per year, compounded monthly, on her savings account. what will be michelle's balance in five years?
Answers: 3
image
Business, 23.06.2019 06:30, jwoodsk7598
Transferable skills necessary for successful employment include a. basic skills b. thinking skills c. personal qualities d. all of the above select the best answer from the choices provided
Answers: 1
Do you know the correct answer?
What will happen to a project's schedule if there are resource overloads and the critical path is de...

Questions in other subjects:

Konu
Advanced Placement (AP), 25.07.2020 22:01