The following table lists the components needed to assemble an end item, the manufacturing or purchase lead times (in weeks) for typical lot sizes, amount on hand, and the direct components of each item and, in brackets, the number of each component for each parent. Item Lead Time Amount on

Hand Direct

Components

End item 1 - L(2), C(1), K(3)

L 2 10 B(2), J(3)

C 3 15 G(2), B(2)

K 3 20 H(4), B(2)

B 2 30

J 3 30

G 3 5

H 2 -
If 40 units of the end item are to be assembled, how many additional units of B are needed? (You don’t need to develop the MRP tables.)
An order for 40 units of the end item is scheduled to be shipped at the start of week 8. What is the latest week that the components of the order can be started and the order still be ready to ship on time? (You don’t need to develop the MRP tables.)

answer
Answers: 3

Other questions on the subject: Business

image
Business, 23.06.2019 00:00, puppy4151
How much is a 2019 tesla? ? exact price trying to buy for my 6 year old sister
Answers: 2
image
Business, 23.06.2019 02:30, maymaaz
Harmon inc. produces joint products l, m, and n from a joint process. information concerning a batch produced in may at a joint cost of $75,000 was as follows:
Answers: 3
image
Business, 23.06.2019 05:20, Geo777
What is difference between fiscal year and tax year? explain in the simplest way.
Answers: 1
image
Business, 23.06.2019 05:30, alani64
When conducting a swot analysis, information about turnover, profit margins, and staff quality can be used to identify:
Answers: 2
Do you know the correct answer?
The following table lists the components needed to assemble an end item, the manufacturing or purcha...

Questions in other subjects:

Konu
Mathematics, 17.12.2020 01:30
Konu
Computers and Technology, 17.12.2020 01:30
Konu
Mathematics, 17.12.2020 01:30