Using the Guth text sections 12.1.1 to 12.1.1.7 explain which Plan Procurement Inputs you might use in your role as a newly assigned project manager. Why? How would you use them? Based on Guthâs text in Section 12.1.1 to 12.1.7 I would use the following Inputs in the Planning Process group of Procurement related activities-
1) Project Management Plan- This is needed because the project management plan will give idea about the list of the goods or services needed to be procured, it will give details about the acceptance criteria and it will also have the WBS (work breakdown structure) which can help in determining budget for each activity. The make or buy analysis will be a helpful tool.
2) Requirements Documents- This document has the details of the requirements of the project. This document details about the procurement activities and details about the various contract documents. The make or buy analysis can be a useful tool.
3) Risk Register- This includes the List of risks, Analysis of risks, and Risk response planning to manage procurement related risks.
4) Project Schedule- The project schedule contains the timelines for the various activities of the project and can be used to determine the required timelines for the services or goods to be procured.
5) Activity Resource Requirements- This document has all the details about resources required for the project, including people, materials and technology, etc.
6) Stakeholder Register- This document has all the details about the various stakeholders in the project. Stakeholders are important for procurement management.
7) OPA (Organizational Process Assets) â This document has the information of the organizationâs current procurement policies and these policies can be helpful in drafting a procurement management plan. This can also help in defining various contracts involved in procurement management.
Thus all of the above Inputs can significantly help to plan Procurement activities in order to generate outputs such as Procurement Management Plan, procurement Statement of Work, Procurement documents, Vendor/supplier source selection criteria and make-or-buy decisions.

answer
Answers: 3

Other questions on the subject: Business

image
Business, 21.06.2019 21:30, jayjay5246
On july 1, 2016, killearn company acquired 103,000 of the outstanding shares of shaun company for $21 per share. this acquisition gave killearn a 40 percent ownership of shaun and allowed killearn to significantly influence the investee's decisions. as of july 1, 2016, the investee had assets with a book value of $6 million and liabilities of $1,468,500. at the time, shaun held equipment appraised at $140,000 above book value; it was considered to have a seven-year remaining life with no salvage value. shaun also held a copyright with a five-year remaining life on its books that was undervalued by $562,500. any remaining excess cost was attributable to goodwill. depreciation and amortization are computed using the straight-line method. killearn applies the equity method for its investment in shaun. shaun's policy is to declare and pay a $1 per share cash dividend every april 1 and october 1. shaun's income, earned evenly throughout each year, was $580,000 in 2016, $606,600 in 2017, and $649,200 in 2018. in addition, killearn sold inventory costing $93,000 to shaun for $155,000 during 2017. shaun resold $97,500 of this inventory during 2017 and the remaining $57,500 during 2018.a. determine the equity income to be recognized by killearn during each of these years. 2016 2017 2018b. compute killearn’s investment in shaun company’s balance as of december 31, 2018.
Answers: 2
image
Business, 22.06.2019 01:00, bommat1085
The following account balances at the beginning of january were selected from the general ledger of fresh bagel manufacturing​ company: work in process inventory ​$0 raw materials inventory $ 29 comma 000 finished goods inventory $ 40 comma 900 additional​ data: 1. actual manufacturing overhead for january amounted to $ 62 comma 600. 2. total direct labor cost for january was $ 63 comma 600. 3. the predetermined manufacturing overhead rate is based on direct labor cost. the budget for the year called for $ 255 comma 000 of direct labor cost and $ 382 comma 500 of manufacturing overhead costs. 4. the only job unfinished on january 31 was job no.​ 151, for which total direct labor charges were $ 5 comma 700 ​(1 comma 000 direct labor​ hours) and total direct material charges were $ 14 comma 400. 5. cost of direct materials placed in production during january totaled $ 123 comma 300. there were no indirect material requisitions during january. 6. january 31 balance in raw materials inventory was $ 35 comma 200. 7. finished goods inventory balance on january 31 was $ 35 comma 400. what is the cost of goods manufactured for​ january
Answers: 1
image
Business, 22.06.2019 06:00, bobbyxii6033
Suppose that a monopolistically competitive restaurant is currently serving 260 meals per day (the output where mr
Answers: 2
image
Business, 22.06.2019 17:50, adamflex
Variable rate cd’s = $90 treasury bills = $150 discount loans = $20 treasury notes = $100 fixed rate cds = $160 money market deposit accts. = $140 savings deposits = $90 fed funds borrowing = $40 variable rate mortgage loans $140 demand deposits = $40 primary reserves = $50 fixed rate loans = $210 fed funds lending = $50 equity capital = $120 a. develop a balance sheet from the above data. be sure to divide your balance sheet into rate-sensitive assets and liabilities as we did in class and in the examples. b. perform a standard gap analysis and a duration analysis using the above data if you have a 1.15% decrease in interest rates and an average duration of assets of 5.4 years and an average duration of liabilities of 3.8 years. c. indicate if this bank will remain solvent after the valuation changes. if so, indicate the new level of equity capital after the valuation changes. if not, indicate the amount of the shortage in equity capital.
Answers: 3
Do you know the correct answer?
Using the Guth text sections 12.1.1 to 12.1.1.7 explain which Plan Procurement Inputs you might use...

Questions in other subjects:

Konu
Mathematics, 03.03.2021 07:30
Konu
Mathematics, 03.03.2021 07:30