A worker-machine operation was found to involve 3.3 minutes of machine time per cycle in the course of 40 cycles of stopwatch study. The worker’s time averaged 1.8 minutes per cycle, and the worker was given a rating of 108 percent (machine rating is 100 percent). Midway through the study, the worker took a 10-minute rest break. Assuming an allowance factor of 8 percent of work time which is applied only to the worker element (not the machine element), determine the standard time for this job.

answer
Answers: 1

Other questions on the subject: Business

image
Business, 22.06.2019 01:40, lb4628830
Select the word from the list that best fits the definition sometimes
Answers: 2
image
Business, 22.06.2019 15:30, bhadd2001
Susan is a 5th grade teacher and loves getting up every day and going to work to teach her students. this is an example of a. extrinsic value b. interests c. intrinsic value d. external value
Answers: 2
image
Business, 22.06.2019 20:50, fathimasaynas2975
Lead time for one of your fastest-moving products is 20 days. demand during this period averages 90 units per day. a) what would be an appropriate reorder point? ) how does your answer change if demand during lead time doubles? ) how does your answer change if demand during lead time drops in half?
Answers: 1
image
Business, 22.06.2019 21:00, kalbaugh
An important source of public scrutiny is "watchdogs." these are: the efforts of a firm's competitors, including how often the competitors attack the firm's strategies. taxpayer-supported government agencies that limit a firm's ability to compete in foreign markets. companies designated by the government to only produce products that support the government defense program. socially conscious groups that make it their mission to measure the social responsibility levels of businesses, and provide consumers with their opinions about the level of corporate responsibility of various companies.