Business, 20.10.2020 20:01, ohgeezy

Greenwood Company manufactures two products—14,000 units of Product Y and 6,000 units of Product Z. The company uses a plantwide overhead rate based on direct labor-hours. It is considering implementing an activity-based costing (ABC) system that allocates all of its manufacturing overhead to four cost pools. The following additional information is available for the company as a whole and for Products Y and Z: Activity Cost Pool Activity Measure Estimated Overhead Cost Expected Activity
Machining Machine-hours $200,000 10,000 MHs
Machine setups Number of setups $100,000 200 setups
Production design Number of products $84,000 2 products
General factory Direct labor-hours $300,000 12,000 DLHs
Activity Measure Product Y Product Z
Machining 8,000 2,000
Number of setups 40 160
Number of products 1 1
Direct labor-hours 9,000 3,000
1. What is the company’s plantwide overhead rate?
2. Using the plantwide overhead rate, how much manufacturing overhead cost is allocated to Product Y and Product Z?
3. What is the activity rate for the Machining activity cost pool?
4. What is the activity rate for the Machine Setups activity cost pool?
5. What is the activity rate for the Product Design activity cost pool?
6. What is the activity rate for the General Factory activity cost pool?
7. Which of the four activities is a batch-level activity?
8. Which of the four activities is a product-level activity?
9. Using the ABC system, how much total manufacturing overhead cost would be assigned to Product Y?
10. Using the ABC system, how much total manufacturing overhead cost would be assigned to Product Z?
11. Using the plantwide overhead rate, what percentage of the total overhead cost is allocated to Product Y and Product Z?
12. Using the ABC system, what percentage of the Machining costs is assigned to Product Y and Product Z?
13. Using the ABC system, what percentage of Machine Setups cost is assigned to Product Y and Product Z? (Round your answers to 2 decimal places.)
14. Using the ABC system, what percentage of the Product Design cost is assigned to Product Y and Product Z?
15. Using the ABC system, what percentage of the General Factory cost is assigned to Product Y and Product Z?

answer
Answers: 1

Other questions on the subject: Business

image
Business, 21.06.2019 15:40, jackie36390
There is a cost associated with each source of financing. discuss the cost of debt, preferred stock, common stock, and retained earnings in detail. which source of financing is typically less expensive? why? why do financial managers try to determine the optimal capital mix? be specific.
Answers: 1
image
Business, 21.06.2019 19:50, Pookaapoo8832
Which of the following best describes the economic effect that results when the government increases interest rates and restricts the lending of money? a. borrowing money becomes more expensive and there is less investment in production. b. the economy grows as investments result in larger profits. c. government spending drives up prices because of greater competition for goods and services. d. consumers save more money and spend less buying goods and services.
Answers: 2
image
Business, 21.06.2019 20:00, tiannaetzel
During 2017, sheridan company expected job no. 26 to cost $300000 of overhead, $500000 of materials, and $200000 in labor. sheridan applied overhead based on direct labor cost. actual production required an overhead cost of $260000, $510000 in materials used, and $150000 in labor. all of the goods were completed. what amount was transferred to finished goods?
Answers: 1
image
Business, 22.06.2019 21:10, kayleerichards666
Acompany has two products: standard and deluxe. the company expects to produce 36,375 standard units and 62,240 deluxe units. it uses activity-based costing and has prepared the following analysis showing budgeted cost and cost driver activity for each of its three activity cost pools. budgeted activity of cost driver activity cost pool budgeted cost standard deluxe activity 1 $ 93,000 2,500 5,250 activity 2 $ 92,000 4,500 5,500 activity 3 $ 87,000 3,000 2,800 what is the overhead cost per unit for the standard units? what is the overhead cost per unit for the deluxe units? (round activity rate and cost per unit answers to 2 decimal places.)activity expected costs expected activity driver activity rate1 93,000 2 92,000 3 87,000 standard activity activity driver activity rate allocated costs1 2 3
Answers: 2
Do you know the correct answer?
Greenwood Company manufactures two products—14,000 units of Product Y and 6,000 units of Product Z....

Questions in other subjects:

Konu
Mathematics, 09.09.2019 02:10
Konu
Law, 09.09.2019 02:10