Tombro Industries is in the process of automating one of its plants and developing a flexible manufacturing system. The company is finding it necessary to make many changes in operating procedures. Progress has been slow, particularly in trying to develop new performance measures for the factory In an effort to evaluate performance and determine where improvements can be made, management has gathered the following data relating to activities over the last four months Month Quality control measures: Number of defects Number of warranty claims Number of customer complaint:s 170 46 103 131 37 86 192 53 109 92 34 65 Material control measures: Purchase order lead time Scrap as a percent of total cost 8 days 7 days 5 days 4 days Machine performance measures: Machine downtime as a percentage of availability Use as a percentage of availability Setup time (hours) 8% 85% 12 95% 92% 10 89% Delivery performance measures: Throughput time Manufacturing cycle efficiency (MCE) Delivery cycle time Percentage of on-time deliveries 968 95% 92% 89% The president has read in industry journals that throughput time, MCE, and delivery cycle time are important measures of performance, but no one is sure how they are computed. You have been asked to assist the company, and you have gathered the following data relating to these measures: Average per Month in days Wait time per order before start of production Inspection time per unit Process time per unit Queue time per unit Move time per unit 9.0 11.812.0 14.0 0.90.80.8 0.8 2.82.42.3 3.9 4.4 5.3 7.3 0.6 0.6 0.9 Required:
1-a. Compute the throughput time for each month
1-b. Compute the manufacturing cycle efficiency (MCE) for each month
1-c. Compute the delivery cycle time for each month.
3 1-a. Compute the throughput time for each month 1-b. Compute the manufacturing cycle efficiency (MCE) for each month
4. Assume that in month 5 the inspection time, process time, and so forth, are the same as for month 4, except that the company is able to completely eliminate the queue time during production using Lean Production. Compute the new throughput time and MCE.
3 1-a. Compute the throughput time for each month 1-b. Compute the manufacturing cycle efficiency (MCE) for each month
3-b. Refer to the inspection time, process time, and so forth, given for month 4. Assume that in month 6 the inspection time, process time, and so forth, are the same as in month 4, except that the company is able to eliminate both the queue time during production and the inspection time using Lean Production. Compute the new throughput time and MCE
1-c. Compute the delivery cycle time for each month (Round your answers to 1 decimal place.)

answer
Answers: 1

Other questions on the subject: Business

image
Business, 22.06.2019 07:10, carlybeavers50
In a team environment, a coordinator is? a person with expert knowledge or skills in a particular area the team needs. a good listener who works to resolve social problems among teammates. a leader who team members focus on their tasks. a good networker who likes to explore new ideas and possiblities.
Answers: 2
image
Business, 22.06.2019 14:00, mrfishyyyy
Your dormitory, griffingate, has appointed you central banker of its economy, which deals in the currency of wizcoins. assume that the velocity of wizcoins in griffingate is constant at 10,000 transactions per year. right now, real gdp is 1,000 wizcoins, and there are 2,000 wizcoins in existence.
Answers: 2
image
Business, 22.06.2019 15:40, kaitlynmorgan43
The cost of direct labor used in production is recorded as a? a. credit to work-in-process inventory account. b. credit to wages payable. c. credit to manufacturing overhead account. d. credit to wages expense.
Answers: 2
image
Business, 22.06.2019 17:30, chilanka
Dr. sperry, a biologist, is using excel to track growth rates of different populations of bacteria. she has a very complex formula in one cell. it begins with “round”. dr. sperry would like to see exactly how excel’s calculation reached the final rounded value that she sees in the cell. what could dr. sperry do to best understand how the calculation was made? try different formulas on her own until she reaches the value shown in excel click on the evaluate formula button in the formulas tab and then click “step in” select the cell and then look at the formula in the formula field of the ribbon remove “round” from the formula in order to see the actual value before rounding
Answers: 2
Do you know the correct answer?
Tombro Industries is in the process of automating one of its plants and developing a flexible manufa...

Questions in other subjects:

Konu
English, 19.10.2021 07:40