Following is the Project Evaluation and Review Technique (PERT) data used to execute a marketing campaign at TeaTime Inc. Calculate the variance for the project in weeks2. Activity Immediate Predecessors Duration Mean (weeks) Duration Variance (weeks2)
A 1 1
B 4 1.5
C A 3 1
D B 1 0.4
E C, D 4 1.5
F E 3 1
G F 5 1.6
a. 2.5 weeks
b. 3.0 weeks
c. 3.5 weeks
d. 4.0 weeks

answer
Answers: 2

Other questions on the subject: Business

image
Business, 21.06.2019 19:20, lukeperry
Astock with a beta of 0.6 has an expected rate of return of 13%. if the market return this year turns out to be 10 percentage points below expectations, what is your best guess as to the rate of return on the stock? (do not round intermediate calculations. enter your answer as a percent rounded to 1 decimal place.)
Answers: 2
image
Business, 22.06.2019 10:00, chancegodwin5
In a small group, members have taken on the task roles of information giver, critic/analyzer, and recorder, and the maintenance roles of gatekeeper and follower. they need to fulfill one more role. which of the following would be most effective for their group dynamics? a dominator b coordinator c opinion seeker d harmonizer
Answers: 1
image
Business, 22.06.2019 11:20, jasalina
In 2000, campbell soup company launched an ad campaign that showed prepubescent boys offering soup to prepubescent girls. the girls declined because they were concerned about their calorie intake. the boys explained that “lots of campbell’s soups are low in calories,” which made them ok for the girls to eat. the ads were pulled after parents expressed concern. why were parents worried? i
Answers: 2
image
Business, 23.06.2019 07:00, jimenagl
Witch design elements is used to organize used to organize the text in orderly fashion?
Answers: 1
Do you know the correct answer?
Following is the Project Evaluation and Review Technique (PERT) data used to execute a marketing cam...

Questions in other subjects: