1. Discuss why many information technology professionals may overlook project cost management and how this might affect completing projects within budget. Many information technology professionals have a poor attitude toward project cost management because they have had bad experiences in the past, they think it is a job for accountants or someone who deals with money and not them. This negative attitude contributes to the poor track record of completing projects within budget. 2. Explain some of the basic principles of cost management, such as profits, life cycle costs, tangible and intangible costs and benefits, direct and indirect costs, reserves, and so on. Cost management involves the process to ensure a project team completes a project within an approved budget. Profits, which are revenues after subtracting expenses. The life cycle costs, includes total cost of ownership or development, plus project support costs. Costs or benefits are tangible, when they are easily measured in dollars. The intangible costs and benefits are difficult to quantify in monetary terms, such as goodwill, prestige, or statements of improved productivity. Direct costs are directly related to producing the products and services of the project at hand, while indirect costs are indirectly related to performing of the project, such as electricity, and paper towels. Reserves are dollars included in a cost estimate to provide a cushion for future situations that are difficult to predict.
3. What is meant by a sunk cost? Give examples of typical sunk costs for an IT project as well as examples from your personal life. Why is it difficult for people to ignore them when they should? A cost that has already been incurred and thus cannot be recovered. The example of a sunk cost from my personal life would be when I bought a new computer and tried to sell it three years later, I cannot make up what money I lost. A typical sunk cost for an IT project would be the cost of getting new software than a month later the software is cheaper than before. Many people fall into the trap of continuing to spend money on a failing project because so much money has been spent on it already.
4. Give examples of when you would prepare rough order of magnitude (ROM), budgetary, and definitive cost estimates for an information technology project. Give an example of using each of the following techniques for creating a cost estimate: analogous, parametric, and bottom-up. When requirements are not in detail and at a very high level, then a determinate solution could be a rough order of magnitude estimate which can vary . In Analogous Estimation, the cost of the project is guessed by comparing it with any similar project previously completed by your organization. Parametric estimation technique uses historical information along with statistical data. The bottom-up estimating technique is also known as the definitive technique. This estimation technique is the most accurate, time-consuming, and costly technique to estimate the cost.
5. Explain what happens during the process to determine the project budget. Project cost budgeting involves allocating the project cost estimate to individual work items over time to create a cost baseline. For example, you may need to break down costs into specific categories like travel, compensation, etc. for each month so

answer
Answers: 1

Other questions on the subject: Business

image
Business, 21.06.2019 21:00, kelseyduhhh
Choose the best term for each definitionexpense, liability, monetary asset, statement of financial position, tangible asset, net worth, market value, investment asset, income, assetitems of monetary value a person or household ownsmoney spentmoney receivedfinancial assets purchased with the hope that they will generate income and appreciate in value to make it possible to sell at a higher price in the futurea debt or obligation owed to othersthe amount you could realistically sell an asset forassets that can be quickly and easily converted into casha measure of financial wealth and indicates the monetary value of all possessions that a person or household owns, minus the total amounts owed to othersa financial statement that describes an individual or family's financial condition on a specified date by showing assets, liabilities, and net worthpersonal property that was purchased to create a lifestyle or improve your life
Answers: 1
image
Business, 22.06.2019 03:20, nakeytrag
The treasurer for pittsburgh iron works wishes to use financial futures to hedge her interest rate exposure. she will sell five treasury futures contracts at $139,000 per contract. it is july and the contracts must be closed out in december of this year. long-term interest rates are currently 7.30 percent. if they increase to 9.50 percent, assume the value of the contracts will go down by 20 percent. also if interest rates do increase by 2.2 percent, assume the firm will have additional interest expense on its business loans and other commitments of $149,000. this expense, of course, will be separate from the futures contracts. a. what will be the profit or loss on the futures contract if interest rates increase to 9.50 percent by december when the contract is closed out
Answers: 1
image
Business, 22.06.2019 19:30, jeanlucceltrick09
Consider the following two projects. both have costs of $5,000 in year 1. project 1 provides benefits of $2,000 in each of the first four years only. the second provides benefits of $2,000 for each of years 6 to 10 only. compute the net benefits using a discount rate of 6 percent. repeat using a discount rate of 12 percent. what can you conclude from this exercise?
Answers: 3
image
Business, 22.06.2019 22:00, nsg0686
Acontractor was awarded a purchase order for commercial items for $1.5 million under the authority of far subpart 13.5. the purchase order was issued in november 2010 and containedall applicable clauses that were current as of the date of the purchase order. under the purchase order, the contractor is required to comply with a small business subcontracting plan that contains all of the required elements. which of the following is true? a. the contractor must submit a standard form 294, subcontracting report for individual contracts. b. the contractor must submit an individual subcontracting report through the electronic subcontracting reporting system (esrs). c. the contractor may submit either an sf 294 or report its subcontracting through esrs. d. the contractor is not required to submit any subcontracting reports.
Answers: 1
Do you know the correct answer?
1. Discuss why many information technology professionals may overlook project cost management and ho...