Business, 12.08.2020 08:01, daionagreene3486

You are developing a performance progress report for a project you are managing. The following time-phased budget was developed earlier in the planning stage and is being used as the standard against which the project performance is measured. Work Packages W1 W2 W3 W4 W5 W6 W7 W8 W9 W10 W11
10 4 9
3 2 10
8 6 10 4 9
10 4 9 3 2 10 8 6 10 4 9
Total You are analyzing the project performance at the end of Week 8. Activity "C" is 20% complete and its actual cost is 5. What is the Cost Performance Index of this activity? Use two decimal places in your calculations.

answer
Answers: 1

Other questions on the subject: Business

image
Business, 21.06.2019 22:10, maddy6882
You have just received notification that you have won the $2.0 million first prize in the centennial lottery. however, the prize will be awarded on your 100th birthday (assuming you're around to collect), 66 years from now. what is the present value of your windfall if the appropriate discount rate is 8 percent?
Answers: 1
image
Business, 22.06.2019 20:30, Arealbot
Afirm wants to hire a project manager (pm) at a salary of $100,000. 30% of pms have high ability, and 70% of pms have low ability. high ability pms generate $120,000 in revenue and low ability pms generate $80,000 in revenue. in addition to differences in productivity, high and low ability pms have different outside offers. if a high ability pm is not hired by the firm, she can work for another company at a salary of $80,000. if the low ability pm is not hired by the firm, she can work for another company for $70,000. high ability pms are also able to get a project management professional (pmp) certification at a cost of $1,000. low ability pms are unable to get a pmp certification (they would fail the test). the firm is not able to observe a pm’s ability, but is able to observe and verify whether or not the pm has a pmp certificate.(a) draw the extensive form of the game. expert answer
Answers: 3
image
Business, 22.06.2019 22:10, tilsendt
Scoresby co. uses 6 machine hours and 2 direct labor hours to produce product x. it uses 8 machine hours and 16 direct labor hours to produce product y. scoresby's assembly and finishing departments have factory overhead rates of $240 per machine hour and $160 per direct labor hour, respectively. how much overhead cost will be charged to the two products? a. product x = $1,440; product y = $2,560 b. product x = $1,760; product y = $4,480 c. product x = $3,200; product y = $9,600 d. product x = $800; product y = $800
Answers: 1
image
Business, 22.06.2019 23:30, bb1593
As a result of a thorough physical inventory, waterway company determined that it had inventory worth $320200 at december 31, 2020. this count did not take into consideration the following facts: walker consignment currently has goods worth $47400 on its sales floor that belong to waterway but are being sold on consignment by walker. the selling price of these goods is $75900. waterway purchased $21900 of goods that were shipped on december 27, fob destination, that will be received by waterway on january 3. determine the correct amount of inventory that waterway should report.
Answers: 2
Do you know the correct answer?
You are developing a performance progress report for a project you are managing. The following time-...

Questions in other subjects:

Konu
Social Studies, 22.08.2019 09:10
Konu
Mathematics, 22.08.2019 09:10