As part of a major plant renovation project, the industrial engineering department has been asked to balance a revised assembly operation to achieve an output of 240 units per eight-hour day. Task times and precedence relationships are as follows:
Task Duration (minutes) Immediate Predecessor
a 0.2 -
b 0.4 a
c 0.2 b
d 0.4 -
e 1.2 d
f 1.2 c
g 1.0 e, f
Do each of the following:
a. Determine the minimum cycle time, the maximum cycle time, and the calculated cycle time.
b. Determine the minimum number of stations needed.
c. Compute the percentage of idle time for the assignment in part d. Use the actual bottleneck cycle time in your calculation.
Answers: 3
Business, 21.06.2019 14:00, myiacoykendall
Jason day company had bonds outstanding with a maturity value of $300,000. on april 30, 2017, when these bonds has an unamortized discount of $10,000, they were called in at 104. to pay for these bonds, day had issued other bonds a month earlier bearing a lower interest rate. the newly issued bonds had a life of 10 years. the new bonds were issued at 103 (face value $300,000).
Answers: 2
Business, 23.06.2019 01:30, caitlynpierce9866
Should i run away or get a boyfriend and be loved again
Answers: 3
Business, 23.06.2019 09:00, aprilstalder
It will gain you more knowledge, intensify your soft skills, grow your strong work ethics and grow your network and grow your network. what is it ?
Answers: 3
Business, 23.06.2019 10:10, dozsyerra
Burnley and co., a graphic design firm, has offices in new york, texas, california, new mexico, and new jersey. each of these offices is headed by a president who reports directly to emma burnley, the ceo. the heads of the centralized hr, finance, and marketing teams report to emma burnley as well. managers in the various offices also report to the ceo directly. based on this information, which of the following statements is most likely to be true? a) emma burnley has a wide span of control. b) burnley and co. has a tall hierarchical structure. c) emma burnley is underworked. d) burnley and co. is a mechanistic organization.
Answers: 3
As part of a major plant renovation project, the industrial engineering department has been asked to...
English, 13.09.2020 20:01
English, 13.09.2020 20:01
Mathematics, 13.09.2020 20:01
Mathematics, 13.09.2020 20:01
Mathematics, 13.09.2020 20:01
Mathematics, 13.09.2020 20:01
Biology, 13.09.2020 20:01
English, 13.09.2020 20:01
Mathematics, 13.09.2020 20:01
Mathematics, 13.09.2020 20:01