Business, 04.08.2020 15:01, valeriam24
An assembly line with 17 tasks is to be balanced. The longest task is 2.4 minutes, and the total time for all tasks is 18 minutes. The line will operate for 450 minutes per day. Required:a. What are the minimum and maximum cycle times? b. What range of daily output is theoretically possible for the line? c. What is the minimum number of workstations needed if the maximum output rate is to be sought?d. What cycle time will provide an output rate of 125 units per day?
Answers: 1
Business, 21.06.2019 23:10, angellove1707
You are the new chief information officer for the video-game developer, necturus games. the company has recently undergone a major expansion of its primary product, and you must staff up the is department and determine the best way to develop new game "capsules" for the game, "escape velocity."
Answers: 1
Business, 22.06.2019 14:30, SophieCasey
The state in which the manufacturing company you work for is located regulates the presence of a particular substance in the environment to concentrations ≤ x. recently-released, reliable research endorsed by the responsible federal agency conclusively demonstrates that the substance poses no risks at concentrations up to 5x. your company has asked you to consider designing a new process with a waste discharge stream containing up to 2x of the substance. based on the stated conditions, describe this possible.
Answers: 2
An assembly line with 17 tasks is to be balanced. The longest task is 2.4 minutes, and the total tim...
Spanish, 20.11.2019 06:31
Mathematics, 20.11.2019 06:31
English, 20.11.2019 06:31