Calculate the latest start for Task B if its predecessor, Task A, finishes on day 3, its succeeding activity, Task E, has a latest start of day 7, and the duration of Task B is 2 days. Select one: a. day 7 b. day 5 c. Cannot be calculated based upon information given. d. day 3

answer
Answers: 1

Other questions on the subject: Business

image
Business, 22.06.2019 00:30, juicyx39
Norton manufacturing expects to produce 2,900 units in january and 3,600 units in february. norton budgets $20 per unit for direct materials. indirect materials are insignificant and not considered for budgeting purposes. the balance in the raw materials inventory account (all direct materials) on january 1 is $38,650. norton desires the ending balance in raw materials inventory to be 10% of the next month's direct materials needed for production. desired ending balance for february is $51,100. what is the cost of budgeted purchases of direct materials needed for january? $58,000 $65,200 $26,550 $25,150
Answers: 1
image
Business, 22.06.2019 01:30, josehernamdez3035
Ben collins plans to buy a house for $166,000. if the real estate in his area is expected to increase in value by 2 percent each year, what will its approximate value be five years from now?
Answers: 1
image
Business, 22.06.2019 05:30, adazeb2003
Find a company that has followed a strong strategic direction- state that generic strategy and the back-up points to support your position.
Answers: 1
image
Business, 23.06.2019 00:40, Cooldude4676
In 2017, "a public university was awarded a federal reimbursement grant" of $18 million to carry out research. of this, $12 million was intended to cover direct costs and $6 million to cover overhead. in a particular year, the university incurred $4 million in allowable direct costs and received $3.4 million from the federal government. it expected to incur the remaining costs and collect the remaining balance in 2018. for 2017 it should recognize revenues from the grant of
Answers: 3
Do you know the correct answer?
Calculate the latest start for Task B if its predecessor, Task A, finishes on day 3, its succeeding...

Questions in other subjects:

Konu
Mathematics, 30.06.2019 13:00
Konu
Social Studies, 30.06.2019 13:00