The following activities are part of a project to be scheduled using CPM:
ACTIVITY IMMEDIATE TIME
PREDECESSOR (WEEKS)
A 6
B A 3
C A 7
D C 2
E B, D 4
F D 3
G E, F 7
a. What is the critical path?
A-B-E-G
A-C-D-E-G
A-C-D-F-G
C-D-F-G
b. How many weeks will it take to complete the project?
Number of weeks
c. How much slack does activity B have?
Slack of activity B weeks
Answers: 1
Business, 22.06.2019 09:40, shybug886
Newton industries is considering a project and has developed the following estimates: unit sales = 4,800, price per unit = $67, variable cost per unit = $42, annual fixed costs = $11,900. the depreciation is $14,700 a year and the tax rate is 34 percent. what effect would an increase of $1 in the selling price have on the operating cash flow?
Answers: 2
Business, 22.06.2019 09:50, thanitoast84
Acar manufacturer uses new machines that automatically assemble an engine from parts fed to the system. the machine can regulate the speed ofassembly depending on the number of parts produced. which type of technology does this machine use? angenoem mense wat ons in matin en esta va ser elthe machine uses
Answers: 3
Business, 22.06.2019 10:20, rockstargirl9245
Asmartphone manufacturing company uses social media to achieve different business objectives. match each social media activity of the company to the objective it the company achieve.
Answers: 1
Business, 22.06.2019 17:30, chrisd2432
Alinguist had a gross income of 53,350 last year. if 17.9% of his income got witheld for federal income tax, how much of the linguist's pay got witheld for federal income tax last year?
Answers: 2
The following activities are part of a project to be scheduled using CPM:
ACTIVITY IMMEDIATE TIME
Mathematics, 18.09.2020 21:01
Mathematics, 18.09.2020 21:01
History, 18.09.2020 21:01
English, 18.09.2020 21:01
Social Studies, 18.09.2020 21:01
Mathematics, 18.09.2020 21:01
History, 18.09.2020 21:01
Mathematics, 18.09.2020 21:01
Physics, 18.09.2020 21:01
Mathematics, 18.09.2020 21:01