Epsilon Co. can produce a unit of product for the following costs: Direct material$8.40
Direct labor24.40
Overhead42.00
Total costs per unit$74.80

An outside supplier offers to provide Epsilon with all the units it needs at $66.20 per unit. If Epsilon buys from the supplier, the company will still incur 30% of its overhead. Epsilon should choose to:

Buy since the relevant cost to make it is $74.80.

Make since the relevant cost to make it is $62.20.

Buy since the relevant cost to make it is $45.40.

Make since the relevant cost to make it is $45.40.

Buy since the relevant cost to make it is $62.20.

answer
Answers: 1

Other questions on the subject: Business

image
Business, 22.06.2019 03:20, nakeytrag
The treasurer for pittsburgh iron works wishes to use financial futures to hedge her interest rate exposure. she will sell five treasury futures contracts at $139,000 per contract. it is july and the contracts must be closed out in december of this year. long-term interest rates are currently 7.30 percent. if they increase to 9.50 percent, assume the value of the contracts will go down by 20 percent. also if interest rates do increase by 2.2 percent, assume the firm will have additional interest expense on its business loans and other commitments of $149,000. this expense, of course, will be separate from the futures contracts. a. what will be the profit or loss on the futures contract if interest rates increase to 9.50 percent by december when the contract is closed out
Answers: 1
image
Business, 22.06.2019 11:00, sbelgirl2000
Consider an economy where government expenditures are 10 and total tax revenues are 10. the supply of labor is fixed at 125 and the supply of capital is fixed at 8. the economy is described by the following equations. y k to the power of 1 divided by 3 end exponent l to the power of 2 divided by 3 end exponent c 2.5 + 0.75 ( y - t ) i 10 - 0.5 r the level of private savings is
Answers: 1
image
Business, 22.06.2019 11:10, AM28
Your team has identified the risks on the project and determined their risk score. the team is in the midst of determining what strategies to put in place should the risks occur. after some discussion, the team members have determined that the risk of losing their network administrator is a risk they'll just deal with if and when it occurs. although they think it's a possibility and the impact would be significant, they've decided to simply deal with it after the fact. which of the following is true regarding this question? a. this is a positive response strategy. b. this is a negative response strategy. c. this is a response strategy for either positive or negative risk known as contingency planning. d. this is a response strategy for either positive or negative risks known as passive acceptance.
Answers: 2
image
Business, 22.06.2019 13:00, Killakyle4744
Amajor advantage of case studies is
Answers: 2
Do you know the correct answer?
Epsilon Co. can produce a unit of product for the following costs: Direct material$8.40
Direc...

Questions in other subjects:

Konu
Mathematics, 23.06.2019 14:00
Konu
Mathematics, 23.06.2019 14:00