A project consists of three activities: A, B, and C. Activities A and B can begin at time 0 (start of the project), but activity C can only start after B is completed. The project ends when all activities are completed. The durations of the activities were simulated 10 times and the following values were obtained: Run A Duration B Duration C Duration 1 51 48 17 2 60 48 19 3 30 39 19 4 31 48 22 5 30 31 14 6 41 16 17 7 44 12 6 8 44 12 10 9 45 43 9 10 60 41 10 Based on the simulated numbers given above, what is the average completion time of the whole project?

answer
Answers: 3

Other questions on the subject: Business

image
Business, 21.06.2019 15:30, jayzelgaspar8441
Jen heard that the bank where she kept her money was going to close for good. jen said she wasn't worried
Answers: 3
image
Business, 21.06.2019 20:30, Deascry
In the rbv are defined as the tangible and intangible assets that a firm controls that it can use to conceive and implement its strategies. answers: management policies
Answers: 1
image
Business, 21.06.2019 21:30, annethelusma25
Which of these things did galileo not do? a. stop publishing his scientific work after being convicted of heresy b. invent the concept of acceleration c. experiment with rolling balls down ramps of increasing steepness to test how objects would fall d. argue that earth moves around the sun e. make up a thought experiment that indicated that objects would fall at the same rate
Answers: 3
image
Business, 22.06.2019 04:00, only1123
Match the type of agreements to their descriptions. will trust living will prenuptial agreement
Answers: 2
Do you know the correct answer?
A project consists of three activities: A, B, and C. Activities A and B can begin at time 0 (start o...

Questions in other subjects:

Konu
Mathematics, 13.04.2021 02:40
Konu
Mathematics, 13.04.2021 02:40