The predetermined manufacturing overhead rate is $10.00 per direct labor hour ($16.00 ÷ 1.6). It was computed from a master manufacturing overhead budget based on normal production of 8,000 direct labor hours (5,000 units) for the month. The master budget showed total variable costs of $60,000 ($7.50 per hour) and total fixed overhead costs of $20,000 ($2.50 per hour). The actual costs for October in producing 4,800 units were as follows.
Direct materials (5,100 pounds) $ 36,720
Direct labor (7,400 hours) 92,500
Variable overhead 59,700
Fixed overhead 21,000
Total manufacturing costs $209,920
The purchasing department buys the quantities of raw materials that are expected to be used in production each month. Raw materials inventories, therefore, can be ignored.
a. Compute all of the materials and labor variances. (Round answers to 0 decimal places, e. g. 125.)
b. Compute the total overhead variance.
![answer](/tpl/images/cats/otvet.png)
Answers: 3
Other questions on the subject: Business
![image](/tpl/images/cats/ekonomika.png)
Business, 22.06.2019 02:40, ItzJuztWillie
The following accounts are denominated in pesos as of december 31, 2015. for reporting purposes, these amounts need to be stated in u. s. dollars. for each balance, indicate the exchange rate that would be used if a translation is made under the current rate method. then, again for each account, provide the exchange rate that would be necessary if a remeasurement is being made using the temporal method. the company was started in 2000. the buildings were acquired in 2002 and the patents in 2003. (round your answers to 2 decimal places.) exchange rates for 1 peso are as follows: 2000 1 peso = $ 0.28 2002 1 = 0.26 2003 1 = 0.25 january 1, 2015 1 = 0.24 april 1, 2015 1 = 0.23 july 1, 2015 1 = 0.22 october 1, 2015 1 = 0.20 december 31, 2015 1 = 0.16 average for 2015 1 = 0.19
Answers: 3
![image](/tpl/images/cats/ekonomika.png)
![image](/tpl/images/cats/ekonomika.png)
Business, 22.06.2019 11:30, barn01
17. chef a says that garnish should be added to a soup right before serving. chef b says that garnish should be cooked with the other ingredients in a soup. which chef is correct? a. chef a is correct. b. both chefs are correct. c. chef b is correct. d. neither chef is correct. student c incorrect which is correct answer?
Answers: 2
![image](/tpl/images/cats/ekonomika.png)
Business, 22.06.2019 21:30, kaitlngley2367
Which is the most compelling reason why mobile advertising is related to big data?
Answers: 1
Do you know the correct answer?
The predetermined manufacturing overhead rate is $10.00 per direct labor hour ($16.00 ÷ 1.6). It was...
Questions in other subjects:
![Konu](/tpl/images/cats/mat.png)
![Konu](/tpl/images/cats/ekonomika.png)
![Konu](/tpl/images/cats/mat.png)
Mathematics, 31.03.2021 01:00
![Konu](/tpl/images/cats/mat.png)
Mathematics, 31.03.2021 01:00
![Konu](/tpl/images/cats/mat.png)
![Konu](/tpl/images/cats/mat.png)
Mathematics, 31.03.2021 01:00
![Konu](/tpl/images/cats/istoriya.png)
![Konu](/tpl/images/cats/mat.png)
![Konu](/tpl/images/cats/en.png)
![Konu](/tpl/images/cats/mat.png)
Mathematics, 31.03.2021 01:00