Subcontractor deliveries are difficult to schedule with the critical chain project methodology because:
A) The project manager cannot force subcontractors to use this project management approach.
B) The feeder buffers for a subcontractor are as much as 50% shorter than for an employee or internal team.
C) Subcontractors routinely operate according to calendar delivery dates.
D) The corporate culture of "no blame" does not naturally extend to subcontractors.
Answers: 2
Business, 22.06.2019 16:00, heavenwagner
In microeconomics, the point at which supply and demand meet is called the blank price
Answers: 3
Business, 22.06.2019 16:50, cutebab4786
Slow ride corp. is evaluating a project with the following cash flows: year cash flow 0 –$12,000 1 5,800 2 6,500 3 6,200 4 5,100 5 –4,300 the company uses a 11 percent discount rate and an 8 percent reinvestment rate on all of its projects. calculate the mirr of the project using all three methods using these interest rates.
Answers: 2
Business, 23.06.2019 00:30, Chen19241
2. which of the following statements about interest is true? a. interest is a one-time fee that you pay for lending money. b. interest is expressed as a percentage of the amount you are borrowing. c. because interest rates tend to be small numbers, they typically don't have much effect on the price of the goods you're purchasing. d. interest is a penalty that you pay when you don't pay your bills on time.
Answers: 1
Subcontractor deliveries are difficult to schedule with the critical chain project methodology becau...
Mathematics, 10.10.2019 22:00
History, 10.10.2019 22:00
English, 10.10.2019 22:00
Social Studies, 10.10.2019 22:00
Mathematics, 10.10.2019 22:00
Mathematics, 10.10.2019 22:00