A contractor intends to bid on a job installing 30 airport security systems. Because this will be a new line of work for the contractor, he believes there will be a learning effect for the job. After reviewing time records from a similar type of activity, the contractor is convinced that an 85 percent curve is appropriate. He estimates that the first job will take his crew eight days to install. How many days should the contractor budget for

a. The first 10 installations?
b. The second 10 installations?
c. The final 10 installations?

answer
Answers: 2

Other questions on the subject: Business

image
Business, 22.06.2019 11:40, avagracegirlp17zx2
On january 1, 2017, sophie's sunlounge owned 4 tanning beds valued at $20,000. during 2017, sophie's bought 3 new beds at a total cost of $14 comma 000, and at the end of the year the market value of all of sophie's beds was $24 comma 000. what was sophie's net investment
Answers: 3
image
Business, 22.06.2019 12:30, asseatingbandit
Sales at a fast-food restaurant average $6,000 per day. the restaurant decided to introduce an advertising campaign to increase daily sales. to determine the effectiveness of the advertising campaign, a sample of 49 days of sales were taken. they found that the average daily sales were $6,300 per day. from past history, the restaurant knew that its population standard deviation is about $1,000. if the level of significance is 0.01, have sales increased as a result of the advertising campaign? multiple choicea)fail to reject the null hypothesis. b)reject the null hypothesis and conclude the mean is higher than $6,000 per day. c)reject the null hypothesis and conclude the mean is lower than $6,000 per day. d)reject the null hypothesis and conclude that the mean is equal to $6,000 per day. expert answer
Answers: 3
image
Business, 22.06.2019 13:40, moneytt2403
Computing equivalent units is especially important for: (a) goods that take a relatively short time to produce, such as plastic bottles. (b) goods with sustainability implications in their production processes. (c) goods that are started and completed during the same period. (d) goods that take a long time to produce, such as airplanes.
Answers: 2
image
Business, 22.06.2019 14:00, tamariarodrigiez
How many months does the federal budget usually take to prepare
Answers: 1
Do you know the correct answer?
A contractor intends to bid on a job installing 30 airport security systems. Because this will be a...

Questions in other subjects:

Konu
English, 17.11.2020 01:00
Konu
Biology, 17.11.2020 01:00
Konu
Physics, 17.11.2020 01:00
Konu
Mathematics, 17.11.2020 01:00