The following schedule was prepared by the production manager of Marymount Metal Shop:

CUTTING POLISHING
Job Start Finish Start Finish
A 0 2 2 5
B 2 6 6 9
C 6 11 11 13
D 11 15 15 20
E 15 17 20 23
F 17 20 23 24
G 20 21 24 28

Determine a schedule that will result in earliest completion of all jobs on this list.

answer
Answers: 1

Other questions on the subject: Business

image
Business, 22.06.2019 14:20, kevinglvz
Anew 2-lane road is needed in a part of town that is growing. at some point the road will need 4 lanes to handle the anticipated traffic. if the city's optimistic estimate of growth is used, the expansion will be needed in 4 years and has a probability of happening of 40%. for the most likely and pessimistic estimates, the expansion will be needed in 8 and 15 years respectively. the probability of the pessimistic estimate happening is 20%. the expansion will cost $ 4.2 million and the interest rate is 8%. what is the expected pw the expansion will cost?
Answers: 1
image
Business, 22.06.2019 17:50, nuggetslices
On january 1, eastern college received $1,350,000 from its students for the spring semester that it recorded in unearned tuition and fees. the term spans four months beginning on january 2 and the college spreads the revenue evenly over the months of the term. assuming the college prepares adjustments monthly, what amount of tuition revenue should the college recognize on february 28?
Answers: 2
image
Business, 22.06.2019 21:20, hailiemanuel3461
Which of the following best explains why large companies pay less for goods from wholesalers? a. large companies are able to pay for the goods they purchase in cash. b. large companies are able to increase the efficiency of wholesale production. c. large companies can buy all or most of a wholesaler's stock. d. large companies have better-paid employees who are better negotiators.
Answers: 2
image
Business, 22.06.2019 22:00, tydukes10
"jake’s roof repair has provided the following data concerning its costs: fixed cost per month cost per repair-hour wages and salaries $ 20,900 $ 15.00 parts and supplies $ 7.70 equipment depreciation $ 2,800 $ 0.35 truck operating expenses $ 5,720 $ 1.60 rent $ 4,690 administrative expenses $ 3,850 $ 0.50 for example, wages and salaries should be $20,900 plus $15.00 per repair-hour. the company expected to work 2,600 repair-hours in may, but actually worked 2,500 repair-hours. the company expects its sales to be $47.00 per repair-hour. required: compute the company’s activity variances for may."
Answers: 1
Do you know the correct answer?
The following schedule was prepared by the production manager of Marymount Metal Shop:

...

Questions in other subjects:

Konu
Mathematics, 25.05.2020 21:01