An error was made by ROC Company in computing the percentage of completion of the current year's ending WIP Inventory. The error resulted in the assignment of a lower percentage of completion to each component of the inventory than actually was the case. There was no beginning WIP Inventory. What is the effect of this error on

(1) cost assigned to cost of goods completed for the period and
(2) the computation of costs per equivalent unit?

a. Understated Overstated
b. Overstated Understated
c. are both Overstated

answer
Answers: 1

Other questions on the subject: Business

image
Business, 22.06.2019 11:00, andregijoe41
Alocal barnes and noble bookstore ordered 80 marketing books but received 60 books. what percent of the order was missing?
Answers: 1
image
Business, 22.06.2019 19:00, nativebabydoll35
In north korea, a farmer’s income is the same as a dentist’s income. in a country with a mixed or market economy, the difference between those two professions might be more than 5 times different. how can you explain the fact that individuals doing the same work in different countries do not earn comparable salaries?
Answers: 1
image
Business, 22.06.2019 19:20, goofy44
Royal motor corp. generates a major portion of its revenues by manufacturing luxury sports cars. however, the company also derives an insignificant percent of its annual revenues by selling its sports merchandise that includes apparel, shoes, and other accessories under the same brand name. which of the following terms best describes royal motor corp.? a. aconglomerate b. a subsidiary c. adominant-businessfirm d. a single-business firm
Answers: 1
image
Business, 22.06.2019 19:50, ahoney2233
Statistical process control charts: a. indicate to the operator the true quality of material leaving the process. b. display upper and lower limits for process variables or attributes and signal when a process is no longer in control. c. indicate to the process operator the average outgoing quality of each lot. d. display the measurements on every item being produced. e. are a graphic way of classifying problems by their level of importance, often referred to as the 80-20 rule.
Answers: 2
Do you know the correct answer?
An error was made by ROC Company in computing the percentage of completion of the current year's end...

Questions in other subjects:

Konu
Mathematics, 11.11.2020 14:00
Konu
English, 11.11.2020 14:00
Konu
Mathematics, 11.11.2020 14:00