In the following MRP planning schedule for Item J, indicate the correct net requirements, planned order receipts, and planned order releases to meet the gross requirements. Lead time is one week. (Leave no cells blank - be certain to enter "0" wherever required.)

WEEK NUMBER

ITEM J 0 1 2 3 4 5
Gross requirements 75 50 70
On-hand 40
Net requirements
Planned order receipt
Planned order release
Period 1 2 3 4 5
Item J
OH = 40
LT = 1
SS = 0
Q = L4L Gross requirements 75 50 70
Scheduled receipts
Projected available balance
Net requirements
Planned order receipts
Planned order releases

answer
Answers: 2

Other questions on the subject: Business

image
Business, 22.06.2019 01:30, whocaresfasdlaf9341
If a firm plans to issue new stock, flotation costs (investment bankers' fees) should not be ignored. there are two approaches to use to account for flotation costs. the first approach is to add the sum of flotation costs for the debt, preferred, and common stock and add them to the initial investment cost. because the investment cost is increased, the project's expected return is reduced so it may not meet the firm's hurdle rate for acceptance of the project. the second approach involves adjusting the cost of common equity as follows: . the difference between the flotation-adjusted cost of equity and the cost of equity calculated without the flotation adjustment represents the flotation cost adjustment. quantitative problem: barton industries expects next year's annual dividend, d1, to be $1.90 and it expects dividends to grow at a constant rate g = 4.3%. the firm's current common stock price, p0, is $22.00. if it needs to issue new common stock, the firm will encounter a 6% flotation cost, f. assume that the cost of equity calculated without the flotation adjustment is 12% and the cost of old common equity is 11.5%. what is the flotation cost adjustment that must be added to its cost of retaine
Answers: 1
image
Business, 22.06.2019 05:00, jason9394
Identify an organization with the low-total-cost value proposition and suggest at least two possible measures within each of the four balanced scorecard perspectives.
Answers: 3
image
Business, 22.06.2019 12:10, huangjianhe135
The following transactions occur for badger biking company during the month of june: a. provide services to customers on account for $32,000. b. receive cash of $24,000 from customers in (a) above. c. purchase bike equipment by signing a note with the bank for $17,000. d. pay utilities of $3,200 for the current month. analyze each transaction and indicate the amount of increases and decreases in the accounting equation. (decreases to account classifications should be entered as a negative.)
Answers: 1
image
Business, 22.06.2019 15:40, Zachary429
Brandt enterprises is considering a new project that has a cost of $1,000,000, and the cfo set up the following simple decision tree to show its three most likely scenarios. the firm could arrange with its work force and suppliers to cease operations at the end of year 1 should it choose to do so, but to obtain this abandonment option, it would have to make a payment to those parties. how much is the option to abandon worth to the firm?
Answers: 1
Do you know the correct answer?
In the following MRP planning schedule for Item J, indicate the correct net requirements, planned or...

Questions in other subjects: