Given the following information for a one-year project, answer the following questions. Recall that PV is the planned value. EV is the earned value, AC is the actual cost, and BAC is the budget at completion.
PV = $23,000
EV = $20,000
AC = $25,000
BAC = $120,000
a. What is the cost variance, schedule variance, cost performance index (CPI), and schedule performance index (SPI) for the project?
b. How is the project doing? Is it ahead of schedule or behind schedule? Is it under budget or over budget?
c. Use the CPI to calculate the estimate at completion (EAC) for this project. Is the project performing better or worse than planned?
d. Use the schedule performance index (SPI) to estimate how long it will take to finish this project.
e. Sketch the earned value chart based on this project

answer
Answers: 3

Other questions on the subject: Business

image
Business, 22.06.2019 13:00, shayneseaton
Reliability and validity reliability and validity are two important considerations that must be made with any type of data collection. reliability refers to the ability to consistently produce a given result. in the context of psychological research, this would mean that any instruments or tools used to collect data do so in consistent, reproducible ways. unfortunately, being consistent in measurement does not necessarily mean that you have measured something correctly. to illustrate this concept, consider a kitchen scale that would be used to measure the weight of cereal that you eat in the morning. if the scale is not properly calibrated, it may consistently under- or overestimate the amount of cereal that’s being measured. while the scale is highly reliable in producing consistent results (e. g., the same amount of cereal poured onto the scale produces the same reading each time), those results are incorrect. this is where validity comes into play. validity refers to the extent to which a given instrument or tool accurately measures what it’s supposed to measure. while any valid measure is by necessity reliable, the reverse is not necessarily true. researchers strive to use instruments that are both highly reliable and valid.
Answers: 1
image
Business, 22.06.2019 17:40, libi052207
Turrubiates corporation makes a product that uses a material with the following standards standard quantity 8.0 liters per unit standard price $2.50 per liter standard cost $20.00 per unit the company budgeted for production of 3,800 units in april, but actual production was 3,900 units. the company used 32,000 liters of direct material to produce this output. the company purchased 20,100 liters of the direct material at $2.6 per liter. the direct materials purchases variance is computed when the materials are purchased. the materials quantity variance for april is:
Answers: 1
image
Business, 22.06.2019 20:20, martinezarielys17
As you have noticed, the demand for flip phones has drastically reduced, and there are only a few consumer electronics companies selling them at extremely low prices. also, the current buyers of flip phones are mainly categorized under laggards. which of the following stages of the industry life cycle is the flip phone industry in currently? a. growth stage b. maturity stage c. decline stage d. commercialization stage
Answers: 2
image
Business, 22.06.2019 20:30, bbby2
1. what is the lowest balance during this period? 2. lily just received her bank statement below. a. what does the bank think her ending balance is? b. how much more does the bank think lily has? c. what transactions are missing? 3. what is the danger of not balancing your bank account? lily’s bank statement deposits: 2/25 $35 2/26 $20 3/1 $256.32 checks: 2/24 ck #301 $25 2/26 #302 $150 debit card: 2/24 american eagle $75.48 2/25 chick fa la $4.67 2/27 mcdonalds $3.56 2/28 chevron $34.76 withdrawal: 2/27 $40 beginning balance $423.34 deposits $311.32 total debits $333.47 ending balance $401.19
Answers: 1
Do you know the correct answer?
Given the following information for a one-year project, answer the following questions. Recall that...

Questions in other subjects:

Konu
Mathematics, 16.04.2021 16:20
Konu
Mathematics, 16.04.2021 16:20