Maintenance at a major theme park in central Florida is an ongoing process that occurs 24 hours a day. Because it is a long drive from most residential areas to the park, employees do not like to work shifts of fewer than eight hours. These eight-hour shifts start every four hours throughout the day. The number of maintenance workers needed at different times throughout the day varies. The following table summarizes the minimum number of employees needed in each four-hour time period.
Time Period Minimum Employees Needed
12 a. m. β 4 a. m. 90
4 a. m. β 8 a. m. 215
8 a. m. β 12 p. m. 250
12 p. m. β 4 p. m. 165
4 p. m. β 8 p. m. 300
8 p. m. β 12 a. m. 125
The maintenance supervisor wants to determine the minimum number of employees to schedule that meets the minimum staffing requirements.
1. Formulate the LP model for this problem.
2. Create the spreadsheet model and use Solver to solve the problem.
Answers: 3
Business, 22.06.2019 19:20, natajayd
The following information is from the 2019 records of albert book shop: accounts receivable, december 31, 2019 $ 42 comma 000 (debit) allowance for bad debts, december 31, 2019 prior to adjustment 2 comma 000 (debit) net credit sales for 2019 179 comma 000 accounts written off as uncollectible during 2017 15 comma 000 cash sales during 2019 28 comma 500 bad debts expense is estimated by the method. management estimates that $ 5 comma 300 of accounts receivable will be uncollectible. calculate the amount of bad debts expense for 2019.
Answers: 2
Business, 22.06.2019 23:00, vipergod07
Customers arrive at rich dunn's styling shop at a rate of 3 per hour, distributed in a poisson fashion. rich can perform an average of 5 haircuts per hour, according to a negative exponential distribution. a) the average number of customers waiting for haircuts= customersb) the average number of customers in the shop= customersc) the average time a customer waits until it is his or her turn= minutesd) the average time a customer spends in the shop= minutese) the percentage of time that rich is busy= percent
Answers: 3
Business, 23.06.2019 13:20, zack66828
John and sue smith are a married couple who file a joint income tax return. they have two children, so they claim a total of 4 exemptions (based on calendar year 2015 tax law, a personal exemption of $4,000 per person or dependent can be deducted from total income). in addition, they have legitimate itemized deductions totaling $25,750. their total income from wages is $237,500. what is the coupleβs taxable income? $195,750 $221,500 $229,500 $205,750
Answers: 3
Maintenance at a major theme park in central Florida is an ongoing process that occurs 24 hours a da...
History, 03.07.2019 16:00
History, 03.07.2019 16:00
Computers and Technology, 03.07.2019 16:00
History, 03.07.2019 16:00
Biology, 03.07.2019 16:00
English, 03.07.2019 16:00