Calculate the earliest finish for Task D if one of its predecessors, Task A, finishes on day 3, its other predecessor, Task C, finishes on day 4, and the duration of Task D is 2 days.

A)day 6
B)day 3
C)day 4

answer
Answers: 3

Other questions on the subject: Business

image
Business, 21.06.2019 21:00, dasiaflowers85
Identifying transactions national park tours co. is a travel agency. the nine transactions recorded by national park tours during may 2019, its first month of operations, are indicated in the following t accounts: cash (1) 75,000 (2) 900 (7) 8,150 (3) 1,600 (4) 6,280 (6) 2,700 (9) 2,500 accounts receivable (5) 12,300 (7) 8,150 supplies (2) 900 (8) 660 equipment (3) 8,000 accounts payable (6) 2,700 (3) 6,400 beth worley, capital (1) 75,000 beth worley, drawing (9) 2,500 fees earned (5) 12,300 operating expenses (4) 6,280 (8) 660 indicate for each debit and each credit (a) whether an asset, liability, owner's equity, drawing, revenue, or expense account was affected and (b) whether the account was increased (+) or decreased account debited account credited transaction type effect type effect (1) (2) (3) (4) (5) (6) (7) (8) (9)
Answers: 3
image
Business, 22.06.2019 16:00, leo4687
Advanced enterprises reports year-end information from 2018 as follows: sales (160,250 units) $968,000 cost of goods sold 641,000 gross margin 327,000 operating expenses 263,000 operating income $64,000 advanced is developing the 2019 budget. in 2019 the company would like to increase selling prices by 14.5%, and as a result expects a decrease in sales volume of 9%. all other operating expenses are expected to remain constant. assume that cost of goods sold is a variable cost and that operating expenses are a fixed cost. should advanced increase the selling price in 2019?
Answers: 3
image
Business, 22.06.2019 20:50, danielanderson12
The following accounts are from last year’s books at s manufacturing: raw materials bal 0 (b) 157,400 (a) 172,500 15,100 work in process bal 0 (f) 523,600 (b) 133,700 (c) 171,400 (e) 218,500 0 finished goods bal 0 (g) 477,000 (f) 523,600 46,600 manufacturing overhead (b) 23,700 (e) 218,500 (c) 27,700 (d) 159,400 7,700 cost of goods sold (g) 477,000 s manufacturing uses job-order costing and applies manufacturing overhead to jobs based on direct labor costs. what is the amount of cost of goods manufactured for the year
Answers: 3
image
Business, 23.06.2019 04:00, lilzaya510
Management training programs, mentoring programs, and coaching systems are examples of
Answers: 1
Do you know the correct answer?
Calculate the earliest finish for Task D if one of its predecessors, Task A, finishes on day 3, its...

Questions in other subjects:

Konu
Mathematics, 02.02.2021 23:00
Konu
Mathematics, 02.02.2021 23:00