For 2014, Thomas Manufacturing uses machine-hours as the only overhead cost-allocation base. The estimated manufacturing overhead costs are $300,000 and estimated machine hours are 50,000. The actual manufacturing overhead costs are $420,000 and actual machine hours are 70,000. Using job costing, the 2014 budgeted manufacturing overhead rate is .
a. $6.50 per machine-hour
b. $4.80 per machine-hour
c. $5.50 per machine-hour
d. $6.00 per machine-hour

answer
Answers: 1

Other questions on the subject: Business

image
Business, 20.06.2019 18:04, reagriffis24
Which is not following is not considered a debit? a) online billing payment b) check cashed c) atm withdraws d) interest earned
Answers: 1
image
Business, 22.06.2019 06:30, brony2199
"in my opinion, we ought to stop making our own drums and accept that outside supplier's offer," said wim niewindt, managing director of antilles refining, n. v., of aruba. "at a price of $21 per drum, we would be paying $4.70 less than it costs us to manufacture the drums in our own plant. since we use 70,000 drums a year, that would be an annual cost savings of $329,000." antilles refining's current cost to manufacture one drum is given below (based on 70,000 drums per year):
Answers: 1
image
Business, 22.06.2019 19:00, mazolethrin3461
The following are budgeted data: january february march sales in units 16,200 22,400 19,200 production in units 19,200 20,200 18,700 one pound of material is required for each finished unit. the inventory of materials at the end of each month should equal 20% of the following month's production needs. purchases of raw materials for february would be budgeted to be:
Answers: 3
image
Business, 22.06.2019 22:20, arisworlld
With q7 assume the sweet company uses a plantwide predetermined overhead rate with machine-hours as the allocation base. and for q 10,11,13,and 14,assume that the company use department predetermined overhead rates with machine-hours as the allocation bade in both departements.7. assume that sweeten company used cost-plus pricing (and a markup percentage of 80% of total manufacturing cost) to establish selling prices for all of its jobs. what selling price would the company have established for jobs p and q? what are the selling prices for both jobs when stated on a per unit basis assuming 20 units were produced for job p and 30 units were produced for job q? (do not round intermediate calculations. round your final answers to nearest whole dollar.)total price for the job for job p -job q selling price per unit for job p q . how much manufacturing overhead was applied from the molding department to job p and how much was applied to job q? (do not round intermediate calculations.) job p job q manufacturing overhead applied for job p for job q . how much manufacturing overhead was applied from the fabrication department to job p and how much was applied to job q? (do not round intermediate calculations.)job p job q manufacturing overhead applied for job p for job q . if job q included 30 units, what was its unit product cost? (do not round intermediate calculations. round your final answer to nearest whole dollar.)14. assume that sweeten company used cost-plus pricing (and a markup percentage of 80% of total manufacturing cost) to establish selling prices for all of its jobs. what selling price would the company have established for jobs p and q? what are the selling prices for both jobs when stated on a per unit basis assuming 20 units were produced for job p and 30 units were produced for job q? (do not round intermediate calculations. round your final answer to nearest whole dollar.)total price for the job p for job q selling price per unit for job p for job q
Answers: 1
Do you know the correct answer?
For 2014, Thomas Manufacturing uses machine-hours as the only overhead cost-allocation base. The est...

Questions in other subjects:

Konu
Mathematics, 08.01.2020 03:31