: A project has just completed the 87th item in its plan. It was scheduled to have spent $168,000 at this point in the plan, but has actually spent only $156,000. The foreman estimates that the value of the work actually finished is about $162,000. What are the spending and schedule variances for the project? What are the SPI and CPI?

answer
Answers: 3

Other questions on the subject: Business

image
Business, 22.06.2019 00:50, tommyaberman
Suppose that: 1. malaysia requires 1 hour of labor to produce 1 pound of rice and 2 hours of labor to produce 1 pencil; 2. indonesia requires 2 hours of labor to produce 1 pound of rice and 4 hours of labor to produce 1 pencil; 3. each country has 10,000 hours of labor to allocate between the production of rice and pencils; and 4. in autarky, malaysia consumes 5,000 pounds of rice and 2,500 pencils. which country has an absolute advantage in rice production? in pencil production? which country has a comparative advantage in rice production? in pencil production? will trade between the two countries be mutually beneficial?
Answers: 1
image
Business, 22.06.2019 13:30, Hcalhoun21
How does hipaa address employee’s access to e-phi?
Answers: 1
image
Business, 22.06.2019 16:30, AriaMartinez
Corrective action must be taken for a project when (a) actual progress to the planned progress shows the progress is ahead of schedule. (b) the technical specifications have been met. (c) the actual cost of the activities is less than the funds received for the work completed. (d) the actual progress is less than the planned progress.
Answers: 2
image
Business, 22.06.2019 20:00, krystynas799
In myanmar, six laborers, each making the equivalent of $ 2.50 per day, can produce 40 units per day. in china, ten laborers, each making the equivalent of $ 2.25 per day, can produce 48 units. in billings comma montana, two laborers, each making $ 60.00 per day, can make 102 units. based on labor cost per unit only, the most economical location to produce the item is china , with a labor cost per unit of $ . 05. (enter your response rounded to two decimal places.)
Answers: 3
Do you know the correct answer?
: A project has just completed the 87th item in its plan. It was scheduled to have spent $168,000 at...

Questions in other subjects: