6. A project to build a new taxiway at Culpepper Airport is 5 days behind at day 65. It had a planned cost of $735,000 for this point in time, but the actual cost is only $550,000. Estimate the variances

answer
Answers: 3

Other questions on the subject: Business

image
Business, 22.06.2019 12:30, asseatingbandit
Sales at a fast-food restaurant average $6,000 per day. the restaurant decided to introduce an advertising campaign to increase daily sales. to determine the effectiveness of the advertising campaign, a sample of 49 days of sales were taken. they found that the average daily sales were $6,300 per day. from past history, the restaurant knew that its population standard deviation is about $1,000. if the level of significance is 0.01, have sales increased as a result of the advertising campaign? multiple choicea)fail to reject the null hypothesis. b)reject the null hypothesis and conclude the mean is higher than $6,000 per day. c)reject the null hypothesis and conclude the mean is lower than $6,000 per day. d)reject the null hypothesis and conclude that the mean is equal to $6,000 per day. expert answer
Answers: 3
image
Business, 22.06.2019 13:30, lemmeboiz43
The fiscal 2016 financial statements of nike inc. shows average net operating assets (noa) of $8,450 million, average net nonoperating obligations (nno) of $(4,033) million, average total liabilities of $9,014 million, and average equity of $12,483 million. the company's 2016 financial leverage (flev) is: select one: a. (0.477) b. (0.559 c. (0.323) d. (0.447) e. there is not enough information to determine the ratio.
Answers: 2
image
Business, 23.06.2019 07:00, kaileyy06
Look at this section of the 1040ez form. will this individual receive a refund? yes no
Answers: 1
image
Business, 23.06.2019 07:50, zitterkoph
Your company is starting a new r& d initiative: a development of a new drug that dramatically reduces the addiction to smoking. the expert team estimates the probability of developing the drug succesfully at 60% and a chance of losing the investment of 40%. if the project is successful, your company would earn profits (after deducting the investment) of 9,000 (thousand usd). if the development is unsuccessful, the whole investment will be lost -1,000 (thousand usd). your company's risk preference is given by the expected utility function: u(x) v1000 +x, where x is the monetary outcome of a project. calculate the expected profit of the project . calculate the expected utility of the project . find the certainty equivalent of this r& d initiative . find the risk premium of this r& d initiative e is the company risk-averse, risk-loving or risk-neutral? why do you think so?
Answers: 3
Do you know the correct answer?
6. A project to build a new taxiway at Culpepper Airport is 5 days behind at day 65. It had a planne...

Questions in other subjects:

Konu
Mathematics, 19.05.2021 17:30
Konu
Social Studies, 19.05.2021 17:30