Your project to obtain charitable donations is now 30 days into a planned 40-day project. The project is divided into 3 activities. The first activity is designed to solicit individual donations. It is scheduled to run the first 25 days of the project and to bring in $25,000. Even though we are 30 days into the project, we still see that we have only 90 percent of this activity complete. The second activity relates to company donations and is scheduled to run for 30 days starting on day 5 and extending through day 35. We estimate that even though we should have approximately 83 percent (or more precisely 25/30) of this activity complete, it is actually only 50 percent complete. This part of the project was scheduled to bring in $150,000 in donations. The final activity is for matching funds. This activity is scheduled to run the last 10 days of the project and has not started. It is scheduled to bring in an additional $50,000. So far $175,000 has actually been brought in on the project. Calculate the schedule variance, schedule performance index, cost (actually value in this case) variance, and cost performance index. (Negative values should be indicated by a minus sign. Do not round your intermediate calculations or "variance" values. Round your "performance index" values to 3 decimal places.) Schedule variance $ Schedule performance index Cost variance $ Cost performance index

answer
Answers: 2

Other questions on the subject: Business

image
Business, 22.06.2019 11:10, nat8475
The prebisch–singer hypothesis concludes that: a. technology lowers the cost of manufactured products, so developing countries should see an increase in their terms of trade. b. developing countries experience a long-run decline in their terms of trade, as the demand for primary products in higher-income countries declines relative to their demand for manufactured goods. c. because of unfair trading practices, labor in developing countries is exploited. d. opec has been responsible for a slowdown in the world's standard of living.
Answers: 3
image
Business, 22.06.2019 18:30, fggfg33
Jason started last week with $900 in his checking account. during the week, he wrote the checks below. at the end of the week, jason received a paycheck for $534.59. he recorded all of these transactions in his check register. trans typ./ check no. date description of transaction payment/ debit deposit/ credit (+) balance 900 00 241 12/4 miller's food market 53.21 53 21 groceries 846 79 242 12/7 frank's auto parts 24.05 24 05 oil and filter 822 74 243 12/8 mike's barber shop 15.00 15 00 haircut 807 74 deposit 12/9 paycheck 534.59 534 59 1,342 33 evaluate jason's check register. a. jason did a good job; everything is correct. b. the final balance is wrong; jason did not add everything correctly. c. jason should have written debit instead of deposit for the transaction type. d. jason entered the amount for his paycheck in the wrong column.
Answers: 3
image
Business, 22.06.2019 21:30, schneidersamant9242
Which is cheaper: eating out or dining in? the mean cost of a flank steak, broccoli, and rice bought at the grocery store is $13.04 (money. msn website, november 7, 2012). a sample of 100 neighborhood restaurants showed a mean price of $12.75 and a standard deviation of $2 for a comparable restaurant meal. a. develop appropriate hypotheses for a test to determine whether the sample data support the conclusion that the mean cost of a restaurant meal is less than fixing a comparable meal at home. b. using the sample from the 100 restaurants, what is the p-value? c. at a = .05, what is your conclusion? d. repeat the preceding hypothesis test using the critical value approach
Answers: 3
image
Business, 23.06.2019 15:30, bward04
When filling out paperwork after you've been hired, you must have a: a. hiring sheetb. driver's licensec. social security numberd. copy of your transcript
Answers: 1
Do you know the correct answer?
Your project to obtain charitable donations is now 30 days into a planned 40-day project. The projec...

Questions in other subjects:

Konu
Chemistry, 23.10.2021 04:00
Konu
Mathematics, 23.10.2021 04:00