Consider consecutive processes A-B-C, where process A has a capacity of 20 units per hour, process B has a capacity of 25 units per hour, and process C has a capacity of 30 units per hour. Where would an operations manager want any inventory?

answer
Answers: 1

Other questions on the subject: Business

image
Business, 22.06.2019 12:50, 22iungj
Salaries are $4,500 per week for five working days and are paid weekly at the end of the day fridays. the end of the month falls on a thursday. the accountant for dayton company made the appropriate accrual adjustment and posted it to the ledger. the balance of salaries payable, as shown on the adjusted trial balance, will be a (assume that there was no beginning balance in the salaries payable account.)
Answers: 1
image
Business, 22.06.2019 19:10, keenansimpkinsoy0oqc
Imagine us is a startup that offers high definition 3d prenatal ultrasounds for high-end customers. the service process includes four activities that are conducted in the sequence described below. (the time required for each activity is shown in parentheses): activity 1: welcome a patient and explain the procedure. (20 minutes)activity 2: prep the patient (e. g., show them to the room, apply ultrasound gel). (17 minutes) (*your id number represents the amount of time needed to complete this task)activity 3: take images. (5 minutes)activity 4: discuss diagnostic with patient. (20 minutes)at each location there are employees (servers) s1, s2, and s3. the assignment of tasks to servers is the following: s1 does activities 1 and 2.s2 does activity 3.s3 does activity 4.a. what is the capacity of this process (in customers per hour)? b. suppose 3 patients arrive every hour on average. ignoring any “start of day” or “end of day” effects, what are the utilizations of all three servers (%)? c. suppose each activity can be done by any server and any server can do any set of activities. however, each activity is done by only one server. for example, a possible assignment includes: s1 does activity 1, s2 does activity 2, and s3 does activities 3 and 4. of course, the original assignment of servers to activities is also feasible. what is the maximum capacity of the process (in customers per hour)? d. now consider the capacity measures in (c) and (a), what is the percentage change? why can you improve capacity without using additional resources? (there is no free lunch, right? )note: for all hw assignments, show your process of getting the results. only providing the final answers is not acceptable and will get 0%. if necessary, use a separate sheet of paper to show your work.
Answers: 3
image
Business, 22.06.2019 20:30, maguilarz2005
Contrast two economies that transitioned to capitalism and explain what factors affected the ease kf their transition as welas the “face” of capitalism that each has adopted
Answers: 2
image
Business, 22.06.2019 22:00, chels6058
Acontinental polar air mass foms where
Answers: 1
Do you know the correct answer?
Consider consecutive processes A-B-C, where process A has a capacity of 20 units per hour, process B...

Questions in other subjects: