The following project is at the end of its sixth week. Find the cost and schedule variances. Also, find the CPI and SPI. Then find the critical ratio of the project using earned value calculations. Finally, calculate the ETC and EAC for the project. Comment on the project status. Activity Predecessor Duration (wks) Budget ($) Actual Cost ($) %Completea - 2 300 400 100b - 3 200 180 100c a 2 250 300 100d a 5 600 400 20e b, c 4 400 200 20

answer
Answers: 2

Other questions on the subject: Business

image
Business, 21.06.2019 19:50, love12236
Suppose your rich uncle gave you $50,000, which you plan to use for graduate school. you will make the investment now, you expect to earn an annual return of 6%, and you will make 4 equal annual withdrawals, beginning 1 year from today. under these conditions, how large would each withdrawal be so there would be no funds remaining in the account after the 4th?
Answers: 1
image
Business, 22.06.2019 00:50, katie673
At a roundabout, you must yield to a. already in the roundaboutb. entering the roundaboutc. only if their turn signal is ond. only if they honk at you
Answers: 1
image
Business, 22.06.2019 10:30, cocoapop
You meet that special person and get married. amazingly your spouse has exactly the same income you do 47,810. if your tax status is now married filing jointly what is your tax liability
Answers: 2
image
Business, 22.06.2019 14:30, dabicvietboi
Which of the following is an example of a positive externality? a. promoting generic drugs would benefit people. b. a lower inflation rate would benefit most consumers. c. compulsory flu shots for all students prevents the spread of illness in the general public. d. singapore has adopted a comprehensive savings plan for all workers known as the central provident fund.
Answers: 1
Do you know the correct answer?
The following project is at the end of its sixth week. Find the cost and schedule variances. Also, f...

Questions in other subjects:

Konu
Mathematics, 13.01.2021 01:00