On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,480,000. During 2021, costs of $2,160,000 were incurred with estimated costs of $4,160,000 yet to be incurred. Billings of $2,660,000 were sent, and cash collected was $2,410,000.

In 2022, costs incurred were $2,660,000 with remaining costs estimated to be $3,840,000. 2022 billings were $2,910,000 and $2,635,000 cash was collected. The project was completed in 2023 after additional costs of $3,960,000 were incurred. The company’s fiscal year-end is December 31. Arrow recognizes revenue over time according to percentage of completion.

Required:
1. Compute the amount of revenue and gross profit or loss to be recognized in 2021, 2022, and 2023 using the percentage of completion method.
2a. Prepare journal entries for 2021 to record the transactions described (credit "various accounts" for construction costs incurred).
2b. Prepare journal entries for 2022 to record the transactions described (credit "various accounts" for construction costs incurred).
3a. Prepare a partial balance sheet to show the presentation of the project as of December 31, 2021.
3b. Prepare a partial balance sheet to show the presentation of the project as of December 31, 2022.

answer
Answers: 1

Other questions on the subject: Business

image
Business, 22.06.2019 11:30, iBrain
4.     chef a says that broth should be brought to a boil. chef b says that broth should be kept at an even, gentle simmer. which chef is correct? a. neither chef is correct. b. chef a is correct. c. both chefs are correct. d. chef b is correct. student c   incorrect which is right answer
Answers: 2
image
Business, 22.06.2019 19:00, makaylahunt
James is an employee in the widget inspection department of xyz systems, a government contractor. james was part of a 3-person inspection team that found a particular batch of widgets did not meet the exacting requirements of the u. s. government. in order to meet the tight deadline and avoid penalties under the contract, james' boss demanded that the batch of widgets be sent in fulfillment of the government contract. when james found out, he went to the vice president of the company and reported the situation. james was demoted by his boss, and no longer works on government projects. james has a:
Answers: 3
image
Business, 22.06.2019 21:10, chrisraptorofficial
This problem has been solved! see the answerthe xyz corporation is interested in possible differences in days worked by salaried employees in three departments in the financial area. a survey of 23 randomly chosen employees reveals the data shown below. because of the casual sampling methodology in this survey, the sample sizes are unequal. research question: are the mean annual attendance rates the same for employees in these three departments? days worked last year by 23 employees department days worked budgets (5 workers) 278 260 265 245 258 payables (10 workers) 205 270 220 240 255 217 266 239 240 228 pricing (8 workers) 240 258 233 256 233 242 244 249 picture click here for the excel data filefill in the missing data. (round your p-value to 4 decimal places, mean values to 1 decimal place and other answers to 2group mean n std. dev variancesbudgets payables pricing total one factor anova source ss df ms f p-value treatment error total
Answers: 2
image
Business, 22.06.2019 21:50, preguntassimples
Assume that (i) setups need to be completed first; (ii) a setup can only start once the batch has arrived at the resource, and (iii) all flow units of a batch need to be processed at a resource before any of the units of the batch can be moved to the next resource. process step 1 molding 2 painting 3 dressing setup time 15 min. 30 min. no setup processing time 0.25 min./unit 0.15 min./unit 0.30 min./unit which batch size would minimize inventory without decreasing the process capacity?
Answers: 1
Do you know the correct answer?
On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to b...

Questions in other subjects:

Konu
Mathematics, 07.04.2020 00:10
Konu
Social Studies, 07.04.2020 00:11