A new highway is to be constructed.

Design A calls for a concrete pavement costing $85 per foot with a 16-year life;three paved ditches costing $4 per footeach; and four box culverts every mile, each costing $8,000 and having a 16-year life. Annual maintenance will cost $11,800 permile; the culverts must be cleaned every four years at a cost of$300 each per mile.

Design B calls for a bituminous pavement costing $40 per foot with a 8-year life; two sodded ditches costing $1.40 per foot each; and two pipe culverts every mile, each costing $2,200 and having a 8-year life. The replacement culverts will cost $2,400 each. Annual maintenance will cost $2,900 per mile; the culverts must be cleaned yearly at a cost of $230 each per mile; and the annual ditch maintenance will cost $1.45 per foot per ditch.

Compare the two designs on the basis of equivalent worth per mile for a 16-year period. Find the most economical design on the basis of AW and PW if the MARR is 6% per year.

answer
Answers: 1

Other questions on the subject: Business

image
Business, 21.06.2019 20:30, Dericktopsom
Which of the following pairs is most similar to each other? a. barter goods and fiat money b. digital money and barter goods c. fiat money and digital money d. commodity money and digital money
Answers: 1
image
Business, 22.06.2019 21:10, chrisraptorofficial
This problem has been solved! see the answerthe xyz corporation is interested in possible differences in days worked by salaried employees in three departments in the financial area. a survey of 23 randomly chosen employees reveals the data shown below. because of the casual sampling methodology in this survey, the sample sizes are unequal. research question: are the mean annual attendance rates the same for employees in these three departments? days worked last year by 23 employees department days worked budgets (5 workers) 278 260 265 245 258 payables (10 workers) 205 270 220 240 255 217 266 239 240 228 pricing (8 workers) 240 258 233 256 233 242 244 249 picture click here for the excel data filefill in the missing data. (round your p-value to 4 decimal places, mean values to 1 decimal place and other answers to 2group mean n std. dev variancesbudgets payables pricing total one factor anova source ss df ms f p-value treatment error total
Answers: 2
image
Business, 22.06.2019 23:10, marissasabino111
How are credit unions similar to banks
Answers: 1
image
Business, 23.06.2019 09:40, thomisonariel9800
Max wants to open a basic checking account at his local bank. he needs to bring his and , along with a $50 deposit, to open the account.
Answers: 3
Do you know the correct answer?
A new highway is to be constructed.

Design A calls for a concrete pavement costing $85 p...

Questions in other subjects:

Konu
Mathematics, 28.05.2021 21:20